ᐅ Building an End-Terrace House as a Self-Managed Project with a General Contractor

Created on: 27 May 2019 10:48
G
goalkeeper
Hello everyone,

some of you might have already followed one of my threads about us having to or being allowed to build our end-terrace house on our own responsibility – depending on how you look at it. This means that we are buying an end-terrace plot (215 sqm (2315 sq ft)) in a new development area in the Rhein-Neckar district and will be building on it ourselves – but in coordination with our two terrace neighbors.

The municipality, which sold the plots through a local resident model, ideally wanted applicants to apply as a complete housing group with several families and then build accordingly with a general contractor, construction manager, or architect. Of course, that didn’t really work out, so now there are only individual applicants and also homeowners.

After we were awarded the plot, the addresses of the other terrace neighbors were shared to discuss certain matters, such as roof style, whether or not to have a basement, etc. It was immediately clear that everyone preferred to do their own thing. However, we were still able to agree that the housing group will have a gable roof with a pitch of 35 to 40 degrees (within this 5-degree range).

As the end house, we will build without a basement, while the middle house and the other end house will have basements. This obviously presents a challenge as we would have to make a deep foundation or simply skip it, and the middle house would have to support us, as we will start construction first. The current agreement with the middle house is that we will build a deeper foundation at his expense, as supporting our house later on would be considerably more expensive for him.

We are currently close to signing with the construction manager, the notarization appointment for the plot is at the end of June, and we hope to start construction in the fall of this year. Meanwhile, several other freely planned housing groups are being built around us, which might get in the way with their cranes.

I will document the progress here from time to time – such a self-planned terraced house doesn’t come along very often.
Winniefred27 Apr 2020 14:41
I think you acted correctly. Continuing to rely only on talking could end up being costly later on (if any damage occurs). Of course, this is not a solid foundation for a good neighborly relationship, but you have truly done everything possible to avoid it.

How is everything else in the house?
G
goalkeeper
27 Apr 2020 19:48
Winniefred schrieb:

How is everything else going in the house?

So far, everything is going great. The tiler is almost finished, the staircase was installed last week, and the painter still has about two days of work left. The bathrooms still need the skim coat and some touch-ups with white paint here and there. The drywall installer completed the storage room today.

The painter’s fleece looks absolutely great on the enhanced Q2 wall. The blue wall in the children's room looks much cooler in person.

The sanitary fixtures and the ventilation system installation are still pending but will all be done this week.

Otherwise, the front door will be installed next Monday, and the handover is scheduled for May 7th, followed by the exterior plastering on May 13th.

Construction site staircase with protective film on the steps and temporary railing


Light wooden staircase inside, several steps mounted on white wall, screws visible.


Gray tiles in the bathroom; visible water connections and yellow drain.


Empty room in new build: pink accent wall, two windows, exposed ceiling pipes.


Unfinished room with blue accent wall, two windows, raw concrete floor.


Bathroom with installed bathtub, gray tiles, window on the right, unfinished walls.


Bathroom shell with gray tiles, window on the left, visible water connections.


Dark gray tiled shower with wall niche, concealed cistern, and installation pipes.


Bright unfinished interior with window, construction tools, pipes, and cardboard boxes


Unfinished interior: beige wall, passage in the middle, building materials and rolls in the foreground.
G
goalkeeper
29 Apr 2020 18:08
Now the scratch coat plaster has also been applied in both bathrooms, making the tiles appear noticeably brighter.

Additionally, the guest toilet has been painted for the final time – now we like the tiles even more.

Unfinished bathroom with gray tiles, bathtub, window, and visible installations.


Bathroom under construction: gray tiles, window on the left, installation openings on the wall and baseboard.


Small unfinished bathroom with gray tiles, exposed sanitary connections, and window.
H
halmi
29 Apr 2020 18:34
I really like it.
11ant29 Apr 2020 18:44
halmi schrieb:

Really like it
Me too – but if it were me, I would probably change either the floor format (square) and the layout (diagonal) or the color (darker). Just a suggestion for anyone considering something similar.
https://www.instagram.com/11antgmxde/
https://www.linkedin.com/company/bauen-jetzt/
G
goalkeeper
29 Apr 2020 20:29
11ant schrieb:

The format (square), orientation (diagonal), or color (darker) has been changed. Just a suggestion for those who want to copy it.

...you just come from a different era...