Hello everyone,
This is the construction report following an earlier thread on floor plan design.
Planned are:
618 m² (6650 sq ft) plot of land
150 m² (1615 sq ft) living space
50 m² (540 sq ft) double garage
Air-to-water heat pump with underfloor and wall heating
Zehnder ventilation system
Exterior blinds in the living room, kitchen, and gallery. Windows anthracite on both inside and outside
Smart home wireless Homematic IP
Planned budget: €300,000 including land and ancillary costs + €30,000 reserve
Plus €12,500 net for a 9.6 kWp photovoltaic system financed separately
Only small regional companies recommended by other builders are being considered.
So far, the following trades have been contracted:
Earthworks: €20,000
Shell construction: €73,000 + €1,000 for the porch above the front door, Wienerberger Poroton T9
Roof: €19,000 + €1,500 scaffolding
Electrical work: €11,000 excluding chiseling work
Window materials: 17 Salamander triple-glazed units + Beck & Heun roller shutters + 5 Selt exterior blinds = €16,000
Quotes received for:
Plastering without decorative finish: €21,000
Bathroom ceramics Villeroy & Boch: €3,000 from Reuter Bathroom Shop
Interior doors Herholz: €2,600
Hörmann front door + garage door: €3,000
Building services materials from the internet: €10,000
Zehnder ventilation unit ComfoAir Q350 TR enthalpy heat exchanger including materials: €4,000 from Selfio
Nobilia kitchen furniture: €5,500, Bosch Series 4 kitchen appliances from Für Uns Shop with 50% discount for €3,500
This is the construction report following an earlier thread on floor plan design.
Planned are:
618 m² (6650 sq ft) plot of land
150 m² (1615 sq ft) living space
50 m² (540 sq ft) double garage
Air-to-water heat pump with underfloor and wall heating
Zehnder ventilation system
Exterior blinds in the living room, kitchen, and gallery. Windows anthracite on both inside and outside
Smart home wireless Homematic IP
Planned budget: €300,000 including land and ancillary costs + €30,000 reserve
Plus €12,500 net for a 9.6 kWp photovoltaic system financed separately
Only small regional companies recommended by other builders are being considered.
So far, the following trades have been contracted:
Earthworks: €20,000
Shell construction: €73,000 + €1,000 for the porch above the front door, Wienerberger Poroton T9
Roof: €19,000 + €1,500 scaffolding
Electrical work: €11,000 excluding chiseling work
Window materials: 17 Salamander triple-glazed units + Beck & Heun roller shutters + 5 Selt exterior blinds = €16,000
Quotes received for:
Plastering without decorative finish: €21,000
Bathroom ceramics Villeroy & Boch: €3,000 from Reuter Bathroom Shop
Interior doors Herholz: €2,600
Hörmann front door + garage door: €3,000
Building services materials from the internet: €10,000
Zehnder ventilation unit ComfoAir Q350 TR enthalpy heat exchanger including materials: €4,000 from Selfio
Nobilia kitchen furniture: €5,500, Bosch Series 4 kitchen appliances from Für Uns Shop with 50% discount for €3,500
hegi___ schrieb:
Yes, everywhere. In the shower area, there is a bonded waterproofing layer beneath the tiles.I would say this: on April 6, 2019, we had anhydrite screed installed. Afterwards, we didn’t touch anything except painting the basement and priming the upper floors. Every trade passed the baton without delay, and the earliest we could have moved in was the first week of July. We actually moved in mid-July.So you will 100% be moving into a construction site. But honestly, as long as the house has a finished bathroom and a bedroom to retreat to, it really doesn’t matter.
W
WilderSueden5 Feb 2021 20:48I think with that amount of self-performed work, it’s actually an advantage to live on the construction site 😉
We also moved into a partially finished construction site. We had to save on rent, and well, we had a kitchen, a bathroom, and the children's rooms were ready, so it was manageable. There are definitely worse situations.
hegi___ schrieb:
If necessary, we’ll just move onto a construction site ;-) We’ll see how it goes.
Here’s the continuation with the multi-family house:
https://www.hausbau-forum.de/threads/planung-mehrfamilienhaus-1200-eur-m.38014/That will happen for sure. There’s no “we’ll see.” You can already proactively prepare your wife, girlfriend, children, grandchildren, nieces, and nephews. 🙂Zaba12 schrieb:
That will happen for sure. There’s no “we’ll see.” You can proactively prepare your wife, girlfriend, children, grandchildren, nieces, and nephews. 🙂Experienced readers know that I’m pretty resilient ;-)