ᐅ March 16, 2016: Start of Photovoltaic System Installation

Created on: 16 Mar 2016 10:51
T
T21150
T
T21150
16 Mar 2016 10:51
Today at 10:00 AM, the installation of our new photovoltaic system began.

The approval from the city was granted last week.

Currently, the substructure (Schletter) is being installed.
Tomorrow, the panels will be mounted and the strings routed into the house.

Further electrical installation / inverter setup has not yet been scheduled.

I will keep you updated.

This is an info thread to show how long this process takes, from the first bracket on the roof to commissioning.

Best regards,
Thorsten
T
toxicmolotof
16 Mar 2016 12:25
We needed, excluding snow days and the weekend, 1.5 days. One day for the UK, half a day for panels and connection.
W
Wastl
16 Mar 2016 13:37
I waited about 4 months for the activation/connection from Bayernwerk.
After commissioning, the installer has to come back again when the network operator sells,...
T
toxicmolotof
16 Mar 2016 13:47
Wastl schrieb:
After commissioning, the installer must also get involved again for the grid operator when selling,...

Why?
T
T21150
16 Mar 2016 13:48
Wastl schrieb:
I waited about 4 months for the activation/connection from Bayernwerk.
After commissioning, the installer also has to be involved again when the utility company takes over for the sale,...

Exactly – those are precisely the points I’m curious about.
T
toxicmolotof
16 Mar 2016 13:49
No one else needs to handle that anymore. At least not in NRW.