Today at 10:00 AM, the installation of our new photovoltaic system began.
The approval from the city was granted last week.
Currently, the substructure (Schletter) is being installed.
Tomorrow, the panels will be mounted and the strings routed into the house.
Further electrical installation / inverter setup has not yet been scheduled.
I will keep you updated.
This is an info thread to show how long this process takes, from the first bracket on the roof to commissioning.
Best regards,
Thorsten
The approval from the city was granted last week.
Currently, the substructure (Schletter) is being installed.
Tomorrow, the panels will be mounted and the strings routed into the house.
Further electrical installation / inverter setup has not yet been scheduled.
I will keep you updated.
This is an info thread to show how long this process takes, from the first bracket on the roof to commissioning.
Best regards,
Thorsten
T
toxicmolotof16 Mar 2016 12:25We needed, excluding snow days and the weekend, 1.5 days. One day for the UK, half a day for panels and connection.
T
toxicmolotof16 Mar 2016 13:47Wastl schrieb:
After commissioning, the installer must also get involved again for the grid operator when selling,...Why?
Wastl schrieb:
I waited about 4 months for the activation/connection from Bayernwerk.
After commissioning, the installer also has to be involved again when the utility company takes over for the sale,...Exactly – those are precisely the points I’m curious about.
T
toxicmolotof16 Mar 2016 13:49No one else needs to handle that anymore. At least not in NRW.