ᐅ Preservation of platform supports – zoning plan (building permit / planning permission)

Created on: 13 Dec 2019 22:42
H
Harrybo1981
Hello everyone,
We have received a plot of land from the city. The development plan for our property and the neighboring plots mentions "retention platform support."
I have searched a lot but couldn’t find any information.
Can someone help?
Thanks in advance
Harrybo1981
N
nordanney
15 Dec 2019 00:08
Harrybo1981 schrieb:

This is the only plan available so far.
I already told you to check the website. The zoning plan, explanations, and so on are all posted there. Please just have a look yourself. This is not kindergarten where everything is done for you.
Y
ypg
15 Dec 2019 00:13
I took a quick look. There is an existing building.
I assume the city offers that the “yard” can be retained.
So, “retaining the platform is possible.”
H
Harrybo1981
15 Dec 2019 00:36
Hello
Thanks to everyone
There was an old building on the site, but I was told it has been completely removed
There is nothing left for reuse
That’s why there is some uncertainty
Thank you
Again
11ant15 Dec 2019 02:23
The document titled "Justification" states on page 7: "The development system allows for the temporary preservation of the buildings at Wieslocher Straße 2 (‘platform’) during the initial settlement phase." This means that the buildings at Wieslocher Straße 2 can remain standing while the redevelopment of the site has already begun. The gray shading indicates the existing buildings that are planned to be demolished according to the plan. However, this note does not apply to you if you are interested in a single-family home plot here: it is marked on the site of a multi-family residential block.

P.S.: The “platform” is a counseling center for the homeless.
https://www.instagram.com/11antgmxde/
https://www.linkedin.com/company/bauen-jetzt/
H
Harrybo1981
15 Dec 2019 09:58
Hello 11ant
Thank you very much for the detailed answer.
I might get the plot 14071.
At the moment, there are no buildings on it, and the infrastructure work is still ongoing for the entire area.
As I understand it, plot 14070 is not a residential building but an office.
I want to build without a basement, and a basement is only possible if I remove the existing structure at my own expense.
I will inquire at the town hall tomorrow.
I would like to be sure before I agree.
Thank you,
Harish
K
kbt09
15 Dec 2019 10:02
I don’t see any plot numbers on the design. Which one is 14071?