Hello everyone,
This is the construction report following an earlier thread on floor plan design.
Planned are:
618 m² (6650 sq ft) plot of land
150 m² (1615 sq ft) living space
50 m² (540 sq ft) double garage
Air-to-water heat pump with underfloor and wall heating
Zehnder ventilation system
Exterior blinds in the living room, kitchen, and gallery. Windows anthracite on both inside and outside
Smart home wireless Homematic IP
Planned budget: €300,000 including land and ancillary costs + €30,000 reserve
Plus €12,500 net for a 9.6 kWp photovoltaic system financed separately
Only small regional companies recommended by other builders are being considered.
So far, the following trades have been contracted:
Earthworks: €20,000
Shell construction: €73,000 + €1,000 for the porch above the front door, Wienerberger Poroton T9
Roof: €19,000 + €1,500 scaffolding
Electrical work: €11,000 excluding chiseling work
Window materials: 17 Salamander triple-glazed units + Beck & Heun roller shutters + 5 Selt exterior blinds = €16,000
Quotes received for:
Plastering without decorative finish: €21,000
Bathroom ceramics Villeroy & Boch: €3,000 from Reuter Bathroom Shop
Interior doors Herholz: €2,600
Hörmann front door + garage door: €3,000
Building services materials from the internet: €10,000
Zehnder ventilation unit ComfoAir Q350 TR enthalpy heat exchanger including materials: €4,000 from Selfio
Nobilia kitchen furniture: €5,500, Bosch Series 4 kitchen appliances from Für Uns Shop with 50% discount for €3,500
This is the construction report following an earlier thread on floor plan design.
Planned are:
618 m² (6650 sq ft) plot of land
150 m² (1615 sq ft) living space
50 m² (540 sq ft) double garage
Air-to-water heat pump with underfloor and wall heating
Zehnder ventilation system
Exterior blinds in the living room, kitchen, and gallery. Windows anthracite on both inside and outside
Smart home wireless Homematic IP
Planned budget: €300,000 including land and ancillary costs + €30,000 reserve
Plus €12,500 net for a 9.6 kWp photovoltaic system financed separately
Only small regional companies recommended by other builders are being considered.
So far, the following trades have been contracted:
Earthworks: €20,000
Shell construction: €73,000 + €1,000 for the porch above the front door, Wienerberger Poroton T9
Roof: €19,000 + €1,500 scaffolding
Electrical work: €11,000 excluding chiseling work
Window materials: 17 Salamander triple-glazed units + Beck & Heun roller shutters + 5 Selt exterior blinds = €16,000
Quotes received for:
Plastering without decorative finish: €21,000
Bathroom ceramics Villeroy & Boch: €3,000 from Reuter Bathroom Shop
Interior doors Herholz: €2,600
Hörmann front door + garage door: €3,000
Building services materials from the internet: €10,000
Zehnder ventilation unit ComfoAir Q350 TR enthalpy heat exchanger including materials: €4,000 from Selfio
Nobilia kitchen furniture: €5,500, Bosch Series 4 kitchen appliances from Für Uns Shop with 50% discount for €3,500
hegi___ schrieb:
I think he meant the slightly offset door jamb.Yes, exactly. It was just a joke.
But "slightly offset" is quite flattering.
hegi___ schrieb:
The ground should be filled up all around to the top edge of the base plate. Then you won’t see it anymore. I would suggest making a sketch to see how it is supposed to look. You need to or should extend the insulation over the blocks – if not, then the insulation will be flush with the gravel/paving? Do you plan to backfill against the blocks? The top edge of the base plate should always be above the ground level. You can still manage this with a plinth that has covered and plastered flashing – anything else will inevitably cause construction damage.
hegi___ schrieb:
The concrete slab was finally poured.
Right afterwards, an animal walked over the fresh concrete, of course inside the garage where the concrete remains exposed.How thick is the gravel or crushed stone layer under the slab? In some areas, soil is visible, giving the impression that there is no gravel layer beneath the slab.
Was soil excavated for the blinding layer?
Thank you!
Best regards
Lumpi_LE schrieb:
The base is poorly constructed, creating a significant thermal bridge – unfortunately, it’s too late to change it, or is insulation still going to be added to the walls?Hi,
could you please explain that again in simple terms? What exactly is wrong with the base?
Thanks
Best regards
Wrong might be a bit harsh – it’s better to let the bricks extend beyond the floor slab so that you can insulate flush with the wall.
If you attach the insulation on the outside, then the ground level needs to be 10...20 cm (4...8 inches) above the top edge of the floor slab (rough floor) to be able to cover the insulation with soil.
Due to rain, I would always set the floor slab slightly above the surrounding ground level.
If you attach the insulation on the outside, then the ground level needs to be 10...20 cm (4...8 inches) above the top edge of the floor slab (rough floor) to be able to cover the insulation with soil.
Due to rain, I would always set the floor slab slightly above the surrounding ground level.
BauIwan schrieb:
How thick is the gravel or stone layer beneath the slab? In some areas, the soil is visible, giving the impression that there is no gravel layer under the slab. Was soil excavated for the blinding layer?
Thanks!
Best regardsI believe it is clear from #2 that, unfortunately, there is more than enough gravel under the slab.
I will create a thermal bridge simulation because I am skeptical whether it will make any difference at all.
Similar topics