Good evening,
Our construction company plans to build the exterior walls using an unfilled Poroton T12, 36.5 cm (14 inches) thick. The exterior plaster will consist of a lime-cement plaster between 1.5 and 2 cm (0.6 and 0.8 inches) thick, with a 2 mm (0.08 inch) synthetic resin plaster applied on top. The interior wall plaster will be a machine-applied gypsum plaster.
Is this sufficient for today’s standards? Or would it be better to choose a different Poroton brick?
Best regards, Micha
Our construction company plans to build the exterior walls using an unfilled Poroton T12, 36.5 cm (14 inches) thick. The exterior plaster will consist of a lime-cement plaster between 1.5 and 2 cm (0.6 and 0.8 inches) thick, with a 2 mm (0.08 inch) synthetic resin plaster applied on top. The interior wall plaster will be a machine-applied gypsum plaster.
Is this sufficient for today’s standards? Or would it be better to choose a different Poroton brick?
Best regards, Micha
H
hausbauer26 Dec 2019 08:55I had actually planned to include the unfilled Unipor W08 planer bricks in the construction specifications. The W08 Coriso costs about 40% less in the price list than the 36.5cm (14 inch) planer bricks. I originally did not want insulated blocks, but now I’m really starting to doubt... Maybe larger buyers get completely different prices and, in that specific case, the planer bricks could still be cheaper than the insulated ones? Very unclear.
We currently only have the foundation slab completed, with 6cm (2.4 inches) insulation on the underside. Masonry work with plan T12 Poroton is scheduled for January. Before Christmas, I inquired about the thermal protection certificate and was told it will be handed over to us after completion. Is this procedure correct?
Shouldn’t the energy-saving regulation calculation be available beforehand? In any case, we were always informed that changes are possible as long as they do not affect the structural stability or the energy-saving regulation. The building permit / planning permission has already been applied for, and construction approval (green light in BW) has been granted.
Is there a chance, if the T12 bricks have not yet been ordered, to upgrade to a higher-quality brick since manufacturers are phasing out these “old bricks” to promote newer ones? Are there any experiences with whether general contractors (GCs) are open to such changes?
Shouldn’t the energy-saving regulation calculation be available beforehand? In any case, we were always informed that changes are possible as long as they do not affect the structural stability or the energy-saving regulation. The building permit / planning permission has already been applied for, and construction approval (green light in BW) has been granted.
Is there a chance, if the T12 bricks have not yet been ordered, to upgrade to a higher-quality brick since manufacturers are phasing out these “old bricks” to promote newer ones? Are there any experiences with whether general contractors (GCs) are open to such changes?
H
hausbauer26 Dec 2019 10:32Asking questions doesn’t cost anything... How are the other exterior surfaces of the house constructed? Insulation below or above the foundation slab? Insulation of the top floor ceiling or roof insulation? U-value of the windows?
Hausbauer schrieb:
Questions don't cost anything... How are the remaining exterior surfaces of the house constructed? Insulation below/above the foundation slab? Insulation of the top floor ceiling or roof insulation? U-value of the windows?We are building according to the 2016 Energy Saving Ordinance. Under foundation slab: 6cm (2.4 inches) insulation.
Above foundation slab: 7cm (2.8 inches) insulation.
Perimeter insulation: 6cm (2.4 inches).
Masonry 36.5cm (14.4 inches) T12 Poroton blocks.
Windows: Ug 0.70 W/m²K (U-factor 0.12 Btu/(ft²·h·°F)).
Top floor ceiling insulation: Mineral wool, thermal conductivity 0.035 W/(m·K), 200mm (7.9 inches).
H
hausbauer26 Dec 2019 21:35This all sounds more or less like standard new build quality, except for the masonry. You should ask about the price difference for better insulating masonry; maybe the general contractor doesn’t charge exorbitant prices. You won’t achieve unrealistically high energy savings by improving the U-value from 0.3 to, say, 0.22, but in your position, I would consider paying a few extra euros. Are you heating with a heat pump or gas? Paying attention to proper design of the underfloor heating and correct setting of the heating system can often save as much on energy costs as better U-values of the building envelope.
Similar topics