Hello everyone,
This is the construction report following an earlier thread on floor plan design.
Planned are:
618 m² (6650 sq ft) plot of land
150 m² (1615 sq ft) living space
50 m² (540 sq ft) double garage
Air-to-water heat pump with underfloor and wall heating
Zehnder ventilation system
Exterior blinds in the living room, kitchen, and gallery. Windows anthracite on both inside and outside
Smart home wireless Homematic IP
Planned budget: €300,000 including land and ancillary costs + €30,000 reserve
Plus €12,500 net for a 9.6 kWp photovoltaic system financed separately
Only small regional companies recommended by other builders are being considered.
So far, the following trades have been contracted:
Earthworks: €20,000
Shell construction: €73,000 + €1,000 for the porch above the front door, Wienerberger Poroton T9
Roof: €19,000 + €1,500 scaffolding
Electrical work: €11,000 excluding chiseling work
Window materials: 17 Salamander triple-glazed units + Beck & Heun roller shutters + 5 Selt exterior blinds = €16,000
Quotes received for:
Plastering without decorative finish: €21,000
Bathroom ceramics Villeroy & Boch: €3,000 from Reuter Bathroom Shop
Interior doors Herholz: €2,600
Hörmann front door + garage door: €3,000
Building services materials from the internet: €10,000
Zehnder ventilation unit ComfoAir Q350 TR enthalpy heat exchanger including materials: €4,000 from Selfio
Nobilia kitchen furniture: €5,500, Bosch Series 4 kitchen appliances from Für Uns Shop with 50% discount for €3,500
This is the construction report following an earlier thread on floor plan design.
Planned are:
618 m² (6650 sq ft) plot of land
150 m² (1615 sq ft) living space
50 m² (540 sq ft) double garage
Air-to-water heat pump with underfloor and wall heating
Zehnder ventilation system
Exterior blinds in the living room, kitchen, and gallery. Windows anthracite on both inside and outside
Smart home wireless Homematic IP
Planned budget: €300,000 including land and ancillary costs + €30,000 reserve
Plus €12,500 net for a 9.6 kWp photovoltaic system financed separately
Only small regional companies recommended by other builders are being considered.
So far, the following trades have been contracted:
Earthworks: €20,000
Shell construction: €73,000 + €1,000 for the porch above the front door, Wienerberger Poroton T9
Roof: €19,000 + €1,500 scaffolding
Electrical work: €11,000 excluding chiseling work
Window materials: 17 Salamander triple-glazed units + Beck & Heun roller shutters + 5 Selt exterior blinds = €16,000
Quotes received for:
Plastering without decorative finish: €21,000
Bathroom ceramics Villeroy & Boch: €3,000 from Reuter Bathroom Shop
Interior doors Herholz: €2,600
Hörmann front door + garage door: €3,000
Building services materials from the internet: €10,000
Zehnder ventilation unit ComfoAir Q350 TR enthalpy heat exchanger including materials: €4,000 from Selfio
Nobilia kitchen furniture: €5,500, Bosch Series 4 kitchen appliances from Für Uns Shop with 50% discount for €3,500
B
BackSteinGotik13 Oct 2020 19:51Maschi33 schrieb:
Side note: It’s quite an achievement these days for a construction company to go bankrupt. That’s something you have to manage first...Isn’t the big wave of insolvencies finally clearing up? Starting this month, filings have to be done normally again. The Federal Statistical Office has already identified a huge backlog compared to the previous year without COVID.
You are right… This is not skill but stupidity.
If I go bankrupt despite an almost endless amount of work, and that after 20 years of self-employment, by then a reasonable financial cushion should have been built up. Then the advance work with regular milestone payments is also justifiable (for me it was between 7,000-15,000 euros) in case a client fails to pay.
Besides, most companies are usually happy to be overcharged.
If I go bankrupt despite an almost endless amount of work, and that after 20 years of self-employment, by then a reasonable financial cushion should have been built up. Then the advance work with regular milestone payments is also justifiable (for me it was between 7,000-15,000 euros) in case a client fails to pay.
Besides, most companies are usually happy to be overcharged.
S
sascha-t4-le18 Oct 2020 12:21Hello builder,
Could you give me approximate quantities of how much concrete and masonry were used in your build, in cubic meters?
Your shell construction price is quite low, and I want to check something. I know you have other concerns at the moment.
Best regards
Could you give me approximate quantities of how much concrete and masonry were used in your build, in cubic meters?
Your shell construction price is quite low, and I want to check something. I know you have other concerns at the moment.
Best regards