ᐅ When should you apply for the electricity network connection?
Created on: 16 Apr 2014 08:23
M
Masipulami
Good morning everyone,
We will soon begin the groundwork for the foundation slab.
Now I’m wondering when the best time is to submit the application for the electrical grid connection to the local utility provider?
Can I submit the application now and then schedule a specific appointment once the house has reached a certain stage?
We are building without a basement, so the cable will be routed from the street to the utility room.
How was it with you specifically? At what point did you submit the application, and when was the house connection finally installed?
Thank you in advance for your feedback.
We will soon begin the groundwork for the foundation slab.
Now I’m wondering when the best time is to submit the application for the electrical grid connection to the local utility provider?
Can I submit the application now and then schedule a specific appointment once the house has reached a certain stage?
We are building without a basement, so the cable will be routed from the street to the utility room.
How was it with you specifically? At what point did you submit the application, and when was the house connection finally installed?
Thank you in advance for your feedback.
Is this about the temporary construction power connection?
We also had to wait... about 1.5 months (1.5 months)? Everyone wants to start right now.
Our house construction only began after the power was connected.
After the foundation slab, the mason needs electricity and water; he started about 7 days (7 days) after the foundation slab was completed.
We also had to wait... about 1.5 months (1.5 months)? Everyone wants to start right now.
Our house construction only began after the power was connected.
After the foundation slab, the mason needs electricity and water; he started about 7 days (7 days) after the foundation slab was completed.
First, of course, it’s about the temporary construction power connection. Later, the connection inside the house will follow.
Ok, the application will be submitted later today.
Ok, the application will be submitted later today.
Temporary construction power can be set up independently of your house electrical connection. However, you should try to get your house electrical connection as early as possible. We were able to run the drying phase of the screed using our house power supply. The "regular" electricity is cheaper than temporary construction power.
Ok, thanks again to everyone for your feedback.
The application is completed and on its way to the utility provider. I have also briefly consulted with the utility provider and received confirmation that there will be no waiting times.