Gluecklich27 Mar 2013 20:58Hello again.
It’s heating up... and we are getting deeper into the world of detailed scope of work descriptions and additional costs. Just like here.
Please let us know if the attached figures are really realistic, or if there are any points that might still be missing:
Land leveling 360 €
House surveying 2200 €
Building permit / planning permission fees 465 €
Insurance fees 118 €
Container / waste disposal 480 €
Connections for electricity, water, sewage, gas, sewer sealing 4200 €
Outdoor facilities / terrace 10229 €
Soil report 1260 €
Excavated soil storage 460 €
Filling with excavated soil 460 €
Excavated soil removal 1500 €
Garage 3x9 m (10x30 ft) = 8000 €
Total: 32342 €
What I noticed: construction power supply is missing and possibly the portable toilet.
It’s heating up... and we are getting deeper into the world of detailed scope of work descriptions and additional costs. Just like here.
Please let us know if the attached figures are really realistic, or if there are any points that might still be missing:
Land leveling 360 €
House surveying 2200 €
Building permit / planning permission fees 465 €
Insurance fees 118 €
Container / waste disposal 480 €
Connections for electricity, water, sewage, gas, sewer sealing 4200 €
Outdoor facilities / terrace 10229 €
Soil report 1260 €
Excavated soil storage 460 €
Filling with excavated soil 460 €
Excavated soil removal 1500 €
Garage 3x9 m (10x30 ft) = 8000 €
Total: 32342 €
What I noticed: construction power supply is missing and possibly the portable toilet.
N
nordanney27 Mar 2013 21:54Since the soil testing drilling (four holes) was done today, I can tell you that (at least in the Ruhr area) the costs are around 500-650 EUR. We are also not getting just a basic report...
K
karliseppel28 Mar 2013 10:06Gluecklich schrieb:
Leveling the site 360 €
House surveying 2200 €
Building permit / planning permission fees 465 €
Insurance fees 118 €
Container / waste disposal 480 €
Connections for electricity, water, sewage, gas, waterproofing of sewage 4200 €
Outdoor areas / terrace 10229 €
Soil analysis 1260 €
Storage of excavated material 460 €
Refilling with excavated material 460 €
Removal of excavated material 1500 €
Garage 3x9 = 8000 €
Hi,
how do you arrive at these unusual costs for the excavation?
Those are what I find most questionable.
Is there a quote for the garage? That price seems low to me, or is it a metal construction...?
Otherwise, a foundation under the garage and possibly fill material for the ground beneath the crane is still missing, if you have to take care of that.
B
Bauexperte28 Mar 2013 11:17Hello,
A lot more is still missing – it currently sounds like you want to manage everything on your own? Take a look here:
https://www.hausbau-forum.de/ratgeber/bauherrenhilfe.422/bauherrenhilfe-vor-vertragsabschluss.424/bausumme.662/#Baunebenkosten%20und%20Grunderwerbsteuer
Basically – a detailed itemization is not always necessary – you can expect construction incidental costs of about €35,000–40,000 (thousands) as a good estimate; if the plot is difficult, even more. Plus costs for finishes such as painting and flooring, plus landscaping costs, plus garage costs, plus a reserve for extras.
I am also puzzled by the figures for excavation and removal – where do those come from? Are they based on an existing soil report or estimated for normal ground conditions? The fees for public utility connections also seem quite low at around €4,200. The garage for 3 x 9 meters (10 x 30 feet) is rather cheap – is it a simple steel structure or more like an open carport?
Normally, the site setup – which includes the portable toilet, site vehicles, construction fencing and the waste container – is provided by the main contractor. Why do these items appear in your list?
Best regards, Bauexperte
Gluecklich schrieb:
Please let us know if the attached figures are really realistic, or which points might still be missing:
Land leveling €360
House surveying €2200
Building permit / planning permission fees €465
Insurance fees €118
Container / waste disposal €480
Connections for electricity, water, sewage, gas, sewer sealing €4200
Landscaping / terrace €10,229
Soil survey €1260
Excavation storage €460
Excavation backfilling €460
Excavation removal €1500
Garage 3x9 = €8000
Total: €32,342
What I noticed: Construction power supply is missing and possibly the portable toilet.
A lot more is still missing – it currently sounds like you want to manage everything on your own? Take a look here:
https://www.hausbau-forum.de/ratgeber/bauherrenhilfe.422/bauherrenhilfe-vor-vertragsabschluss.424/bausumme.662/#Baunebenkosten%20und%20Grunderwerbsteuer
Basically – a detailed itemization is not always necessary – you can expect construction incidental costs of about €35,000–40,000 (thousands) as a good estimate; if the plot is difficult, even more. Plus costs for finishes such as painting and flooring, plus landscaping costs, plus garage costs, plus a reserve for extras.
I am also puzzled by the figures for excavation and removal – where do those come from? Are they based on an existing soil report or estimated for normal ground conditions? The fees for public utility connections also seem quite low at around €4,200. The garage for 3 x 9 meters (10 x 30 feet) is rather cheap – is it a simple steel structure or more like an open carport?
Normally, the site setup – which includes the portable toilet, site vehicles, construction fencing and the waste container – is provided by the main contractor. Why do these items appear in your list?
Best regards, Bauexperte
Bauexperte schrieb:
Usually, the site setup—which includes the portable toilet, construction vehicles, site fencing, and waste container—is provided by the contractor. Why do these items appear in your costs?That looks like Danwood or something similar to me. Since I once calculated a Danwood house myself, I know that the two-page building specification didn’t include space for such items, and everything had to be paid for as an additional service.
Gluecklich schrieb:
Hello again.
It’s getting more intense... And we are diving deeper into the world of detailed construction service descriptions and additional costs. Like here.
Please tell us if the attached figures are really realistic, or if some points might still be missing:
Land leveling €360
House surveying €2200
Building permit fees €465
Insurance fees €118
Container / waste disposal €480
Connections for electricity, water, sewer, gas, sewer sealing €4200
Outdoor facilities / terrace €10229
Soil survey €1260
Excavated material storage €460
Filling excavated material €460
Excavated material removal €1500
Garage 3x9 = €8000
Total: €32342
What I noticed: Temporary construction power is missing and possibly the portable toilet.Aside from the fact that, as already noted, not all incidental costs are listed here, I find some of the figures unrealistic.
For the soil survey with 4 boreholes at 6 meters (20 feet) each, we only paid just under €800. A shallower depth would have also been sufficient, but we wanted to be more precise about what might be below.
Building permit fees strongly depend on the project cost; we pay more than double here.
The development connection fees seem extremely low to me! Just the basic charges for electricity and water here (Brandenburg) are over €2000. We don’t need gas (heat pump), but that alone would add about €1000 in basic development fees.
What are the excavation costs based on? We pay around €10,000 for earthworks (excavation including storage—which is not even listed as a separate cost here, so why would it be extra), backfilling with stable material/compaction, and removal, for about 200 m³ (260 yd³) as part of a fixed price contract.
Garage prices vary widely depending on the construction method and materials.
Insurance and waste disposal costs are included in our price, but we are working with a general contractor, not a self-build. From your post, it sounds like you want to do much or all of it as an owner builder?