ᐅ Exterior plaster is uneven, window sills are too short, insulation system is not airtight.

Created on: 30 Dec 2020 23:02
H
Hemingway84
Preface:

We are building a 190 sqm (2,045 sq ft) city villa to KfW 55 energy efficiency standard with a large general contractor (GC) from Königslutter in the Berlin metropolitan area. The GC uses various subcontractors, who in turn work with their own subcontractors (some of whom also hire further subcontractors). So far, several construction defects have occurred. Serious defects were only prevented through our intervention (for example, the formwork for the intermediate ceiling was several centimeters too low and was literally raised five minutes before the concrete was poured). Unfortunately, the site manager is incompetent, thin-skinned, and unobservant. From day one, he has only offered pointless comments and a lack of motivation. He has never recognized defects on his own and has only reluctantly addressed those we reported, often trying to downplay them with standardized phrases.

As a result, we are on site as often as possible because we are constantly on high alert due to the defects encountered so far. Our involvement has already improved or, from our perspective, salvaged many situations. We have also hired a construction supervisor who has occasionally added value, although his passion seems more for photographing the construction than for identifying defects. Sometimes, a simple tape measure or spirit level helps—at least for us.

Our building project is further complicated by the fact that my wife was diagnosed with cancer a few months after purchasing the land and signing the construction contract. A cruel blow of fate, with chemotherapy and all related side effects, framed by the external circumstances of the ongoing COVID-19 pandemic. The loss of income is unfortunate but was anticipated in the financing—albeit as possible parental leave rather than a long-term illness. Nevertheless, it all makes the situation more stressful than it would have been otherwise.

Main section:

We are approaching the completion of the build; the screed drying will finish next week (the scheduled handover is at the end of January, so we just miss out on the VAT reduction). Ninety percent of the house price has already been paid; only the final invoice, expected in the coming weeks, remains outstanding.

At the end of November, the exterior render was applied. At that time and for the days following, outside temperatures did not exceed 5°C (41°F), with some nights dropping below freezing. According to the render manufacturer (Alsecco), the silicate render used may only be applied at temperatures above 5°C (41°F), and temperatures must remain above this threshold in the following days. If not, the render cannot cure properly, which may lead to issues with strength and durability.

One day before the rendering work began, we sent an informal notice of concern to the GC and their construction manager regarding the weather forecast. The subcontractor responded that there was no need to worry and voluntarily offered an additional one year warranty.

The rendering was completed, but even after one week, the exterior render was still soft. In some areas, it “slid,” particularly on the window sills. Please refer to the attached photos for details.

The same subcontractor who applied the external render installed the window sills shortly before (but only after installing the external thermal insulation composite system (ETICS) and the facade reinforcement). The window sills are crooked and uneven. Some also appear to be too short. On average, they protrude only 2–3 cm (1 inch) from the facade. Some are more uneven, for example with one side 1.5 cm (0.6 inch) and the other side 3 cm (1.2 inches). The drip groove on the underside is often flush with the facade. During installation, alcohol was consumed on site, as evidenced by several dozen small drink containers scattered near the scaffolding. It was also apparently easier to cut our up to 3 m (10 ft) long window sills with an angle grinder to fit them into a car, but sealing the joints afterward was forgotten.

The window sills show no visible sealing. According to trade associations, with an ETICS system, there should be two layers of sealing at the window sills. We can see none. It also seems strange that the window sills were cut into the ETICS. The unnecessarily large gaps created were either left unfilled or only filled with silicone or similar, which after more than four weeks remains soft and uncured.

Water constantly accumulates at the edges of the window sills, running down the facade, further softening the render and freezing in places with the render. Where does this water come from? The screed heating program is still running inside, providing warmth. Could this be a sign of leakage around the windows? Indoor humidity is being actively controlled with three drying units, currently below 40% relative humidity. We suspect leakage because at the most affected window corner inside, we found significant residual moisture along with slight bulging of the interior plaster. Elsewhere, the interior plaster appears superficially dry.

The house base was also poorly finished by the same subcontractor. A very thinly scratched-on reinforcing plaster cannot be the waterproof rendering against moisture as specified in the contract. The layer is simply too thin and, according to photos, remains damp even without rain.

Outlook:

What happens next? The defects have been reported, documented with photos, and recorded. Should we still carry out a conditional acceptance with these defects, or refuse acceptance entirely? We would like to move in by the end of February, as my wife begins her follow-up treatment after chemotherapy in March and does not want the stress of moving to undo all her recovery. The potential double burden is not insignificant.

The render is visibly deteriorated and crumbly, patchy, and simply poorly done. In our opinion, it must be completely removed and redone. The window sills should also be removed and replaced because they are too short and partially cut with an angle grinder without technical necessity. We are particularly worried about the sealing and possible damage to the ETICS. Who knows what will happen in a few years.

Next week, at our own expense, we will engage a publicly appointed expert in painting and decorating to assess the severity of the damage and necessary repairs. From our experience, we expect little or no support from the GC or site manager. We intend to stand firm and will not accept repair work or financial compensation. At this point, we only see one solution: starting over completely. This would be very expensive and could become particularly interesting regarding payment of the final invoice.

The GC has only provided us with a 5% retention guarantee for completion, which likely would not cover a full re-execution of the defective work (and according to the contract text, may only be retained after handover for serious defects). Referring to this guarantee, he has already indicated that he insists on full payment upon acceptance, as we have this guarantee as security and it could be increased or extended.

Any advice, comments, ideas, or suggestions are welcome. I just needed to vent a bit. Sometimes you really feel helpless and lost as a client.

Exterior wall of a modern house facade with a window, earthworks visible


Exterior wall with rough render texture, black stone strip above, moisture marks and dust on the ground.


Exterior wall with rough render texture, vertical render crack below dark window sill.


Close-up of a rough sandstone column on a black granite slab; background with houses.


Close-up of a rough brown wall with white sealing compound in the joint above stone slab.


Exterior view of a gray two-story house with a brown upper section, windows, and door.


White rough wall with a black panel protruding from it and flaking edges.


Exterior wall corner: black granite threshold over white render wall, sealing compound visible.


Wall with moisture damage and flaking render; dusty floor next to a window.


Exterior view of a new build house: dark window sill, white base, loose soil in front.
H
Hemingway84
4 Jan 2021 20:00
Hausbau0815 schrieb:

Oh man, when things go wrong, they really go wrong. But it has to get better again sometime! Two months ago, a left-turning vehicle crashed into our Vito. We were completely not at fault, repair costs over €10,000 (over $11,000), and according to the other party’s insurance, the vehicle value was only €3,800 ($4,200), so they declared it a total economic loss. But that’s not true because it can be replaced for under €8,000 ($8,900). The car is now parked in the driveway and can’t be used because it’s not roadworthy. However, I can’t get it repaired either. So it’s lawyer time again. At least does your comprehensive insurance cover it?

Could it be that the roof membrane isn’t waterproof if water is sitting above the vapor barrier? We’ve had that happen too.
And also a leaking vapor barrier. You can check out the pictures in my thread "Dry Construction and Vapor Barrier Done Differently." We had to take down the entire drywall again. I can understand what you’re going through. There were times I didn’t even feel like going to the construction site anymore.
From this perspective, I don’t think a painting consultant makes sense anymore. You need someone who looks at the whole mess and can put a financial figure on it. Also, prepare yourself for the possibility that moving in will be delayed, even though that’s hard to accept.


Regarding the accident: The vehicle involved has now been identified; let’s see what comes out of it in the next few days.

Regarding the leak: No clue yet. The general contractor took a heavy hit yesterday (see below) – so it remains to be seen who will address this issue and when. I’m not going up there fiddling with the vapor retarder for now.

Email from last night:

1. An addition to the facade defect, which is getting worse. Clear demand to replace the site manager for our project and bring in external expertise. Deadline set for January 15th. However, based on experience, nobody will respond or at least make a specific statement on it.
2. Deficiency report concerning moisture penetration above the vapor barrier.
3. Deficiency report regarding our indoor-installed heat pump / controlled ventilation system combo (Vaillant recocompact exclusive). It hasn’t been working properly for weeks. At first, the compressor didn’t start during the screed heating program (it ran only on the heating cartridge, causing huge electricity costs), and now it keeps showing constant error messages. On top of that, the wall penetrations are leaking because one installed part is too short (I can look past the HVAC fitter on the ventilation duct to the outside).

Regarding point 3, the plumber snapped at me today again, saying that while these issues are justified, I should handle everything through the general contractor or site manager and that we’re only one of many clients. I’m doing that, but since nobody responds, he’s always on CC.

Do you sometimes just want to blow up? I don’t care anymore if they have 50 or more projects running simultaneously that they can’t handle. Taking on everything but only working half-heartedly everywhere is no solution. Apparently, they don’t care either that I’m paying nearly €400,000 ($445,000) for the house, working full-time, taking care of my wife, and still acting as the construction clown. Empathy isn’t a one-way street!
Snowy36 schrieb:

What’s your current situation? Are you renting and do you have to move in?


We’re renting and have given notice for February 28th. However, there’s no new tenant yet because the owner wants to inspect the apartment at the end of January first, as he’s considering selling it. So we could probably stay another 1-2 months.

Financially, it would be easier since we’ve already lost about €10,000 ($11,200) due to my wife’s long-term illness. February was also the contractually guaranteed completion date. We could, of course, enforce compensation for delay claims properly, making a later move-in less severe.

We also wanted to be out of the old apartment before my wife’s one-month outpatient rehabilitative treatment 650 km (400 miles) away, so she could focus on herself. But I guess that train has already left.
Hausbau08154 Jan 2021 20:29
Hemingway84 schrieb:

Regarding the accident: the vehicle has now been identified, let’s see what comes of it in the next few days.

At least a small ray of hope.
Hemingway84 schrieb:

Do you sometimes just feel like exploding? I don’t care anymore if they have 50 or more projects running at the same time and can’t handle it. Taking on everything possible but only working at half capacity everywhere doesn’t work. They obviously don’t care that I’m paying around 400,000 EUR (about 400,000 USD) for the house, working full time, caring for my wife, and still playing the role of site clown. Understanding is definitely not a one-way street!

Absolutely. That’s perfectly normal. I have a 1 x 1 meter (about 3 x 3 feet) storage room in the basement. I’d love to wall up GU1 in there.
Tolentino4 Jan 2021 21:52
My condolences. I hope everything turns out well...
Hausbau08154 Jan 2021 21:54
Tolentino schrieb:

My condolences. I hope everything turns out well...

Well, we don’t need condolences, but rather luck and strong nerves.
Wolkensieben5 Jan 2021 02:33
Hemingway84 schrieb:

P.S.: Is it allowed to name the general contractor and/or the site manager? They seem to be keen on cleaning up blogs/forums/reviews online.

I can only speak from experience that you shouldn’t share such information voluntarily, even though that is unfortunate for future homeowners.

However, if someone directly asks you and you provide truthful information, they can’t do anything about it. But you must be able to prove it.

Ideally, a homeowner who has been wronged by a contractor will come to you, and you can show them one of your many folders containing correspondence and lawyer’s letters.

If you are "lucky" enough to have dealt with someone who also scams local tradespeople, that person is “burned” and soon will be gone.

In the worst case, they move to another area and continue their misconduct there.
Hausbau08155 Jan 2021 06:16
Wolkensieben schrieb:

If you’re “lucky” enough to have dealt with someone who also cheats local contractors, that person is “burned” and soon gone.

In the worst case, they move to another area and continue their mischief there.

Unfortunately, I cannot confirm that. My former general contractor cheated both contractors and clients, shut down his company, and started two new ones. He still lives in the same area as before and carries on without a problem. I only know that about a year ago he spent a week in the hospital because of a disagreement with evening visitors.