ᐅ Exterior plaster is uneven, window sills are too short, insulation system is not airtight.

Created on: 30 Dec 2020 23:02
H
Hemingway84
Preface:

We are building a 190 sqm (2,045 sq ft) city villa to KfW 55 energy efficiency standard with a large general contractor (GC) from Königslutter in the Berlin metropolitan area. The GC uses various subcontractors, who in turn work with their own subcontractors (some of whom also hire further subcontractors). So far, several construction defects have occurred. Serious defects were only prevented through our intervention (for example, the formwork for the intermediate ceiling was several centimeters too low and was literally raised five minutes before the concrete was poured). Unfortunately, the site manager is incompetent, thin-skinned, and unobservant. From day one, he has only offered pointless comments and a lack of motivation. He has never recognized defects on his own and has only reluctantly addressed those we reported, often trying to downplay them with standardized phrases.

As a result, we are on site as often as possible because we are constantly on high alert due to the defects encountered so far. Our involvement has already improved or, from our perspective, salvaged many situations. We have also hired a construction supervisor who has occasionally added value, although his passion seems more for photographing the construction than for identifying defects. Sometimes, a simple tape measure or spirit level helps—at least for us.

Our building project is further complicated by the fact that my wife was diagnosed with cancer a few months after purchasing the land and signing the construction contract. A cruel blow of fate, with chemotherapy and all related side effects, framed by the external circumstances of the ongoing COVID-19 pandemic. The loss of income is unfortunate but was anticipated in the financing—albeit as possible parental leave rather than a long-term illness. Nevertheless, it all makes the situation more stressful than it would have been otherwise.

Main section:

We are approaching the completion of the build; the screed drying will finish next week (the scheduled handover is at the end of January, so we just miss out on the VAT reduction). Ninety percent of the house price has already been paid; only the final invoice, expected in the coming weeks, remains outstanding.

At the end of November, the exterior render was applied. At that time and for the days following, outside temperatures did not exceed 5°C (41°F), with some nights dropping below freezing. According to the render manufacturer (Alsecco), the silicate render used may only be applied at temperatures above 5°C (41°F), and temperatures must remain above this threshold in the following days. If not, the render cannot cure properly, which may lead to issues with strength and durability.

One day before the rendering work began, we sent an informal notice of concern to the GC and their construction manager regarding the weather forecast. The subcontractor responded that there was no need to worry and voluntarily offered an additional one year warranty.

The rendering was completed, but even after one week, the exterior render was still soft. In some areas, it “slid,” particularly on the window sills. Please refer to the attached photos for details.

The same subcontractor who applied the external render installed the window sills shortly before (but only after installing the external thermal insulation composite system (ETICS) and the facade reinforcement). The window sills are crooked and uneven. Some also appear to be too short. On average, they protrude only 2–3 cm (1 inch) from the facade. Some are more uneven, for example with one side 1.5 cm (0.6 inch) and the other side 3 cm (1.2 inches). The drip groove on the underside is often flush with the facade. During installation, alcohol was consumed on site, as evidenced by several dozen small drink containers scattered near the scaffolding. It was also apparently easier to cut our up to 3 m (10 ft) long window sills with an angle grinder to fit them into a car, but sealing the joints afterward was forgotten.

The window sills show no visible sealing. According to trade associations, with an ETICS system, there should be two layers of sealing at the window sills. We can see none. It also seems strange that the window sills were cut into the ETICS. The unnecessarily large gaps created were either left unfilled or only filled with silicone or similar, which after more than four weeks remains soft and uncured.

Water constantly accumulates at the edges of the window sills, running down the facade, further softening the render and freezing in places with the render. Where does this water come from? The screed heating program is still running inside, providing warmth. Could this be a sign of leakage around the windows? Indoor humidity is being actively controlled with three drying units, currently below 40% relative humidity. We suspect leakage because at the most affected window corner inside, we found significant residual moisture along with slight bulging of the interior plaster. Elsewhere, the interior plaster appears superficially dry.

The house base was also poorly finished by the same subcontractor. A very thinly scratched-on reinforcing plaster cannot be the waterproof rendering against moisture as specified in the contract. The layer is simply too thin and, according to photos, remains damp even without rain.

Outlook:

What happens next? The defects have been reported, documented with photos, and recorded. Should we still carry out a conditional acceptance with these defects, or refuse acceptance entirely? We would like to move in by the end of February, as my wife begins her follow-up treatment after chemotherapy in March and does not want the stress of moving to undo all her recovery. The potential double burden is not insignificant.

The render is visibly deteriorated and crumbly, patchy, and simply poorly done. In our opinion, it must be completely removed and redone. The window sills should also be removed and replaced because they are too short and partially cut with an angle grinder without technical necessity. We are particularly worried about the sealing and possible damage to the ETICS. Who knows what will happen in a few years.

Next week, at our own expense, we will engage a publicly appointed expert in painting and decorating to assess the severity of the damage and necessary repairs. From our experience, we expect little or no support from the GC or site manager. We intend to stand firm and will not accept repair work or financial compensation. At this point, we only see one solution: starting over completely. This would be very expensive and could become particularly interesting regarding payment of the final invoice.

The GC has only provided us with a 5% retention guarantee for completion, which likely would not cover a full re-execution of the defective work (and according to the contract text, may only be retained after handover for serious defects). Referring to this guarantee, he has already indicated that he insists on full payment upon acceptance, as we have this guarantee as security and it could be increased or extended.

Any advice, comments, ideas, or suggestions are welcome. I just needed to vent a bit. Sometimes you really feel helpless and lost as a client.

Exterior wall of a modern house facade with a window, earthworks visible


Exterior wall with rough render texture, black stone strip above, moisture marks and dust on the ground.


Exterior wall with rough render texture, vertical render crack below dark window sill.


Close-up of a rough sandstone column on a black granite slab; background with houses.


Close-up of a rough brown wall with white sealing compound in the joint above stone slab.


Exterior view of a gray two-story house with a brown upper section, windows, and door.


White rough wall with a black panel protruding from it and flaking edges.


Exterior wall corner: black granite threshold over white render wall, sealing compound visible.


Wall with moisture damage and flaking render; dusty floor next to a window.


Exterior view of a new build house: dark window sill, white base, loose soil in front.
P
parcus
16 Jan 2021 12:55
Just to clarify, I haven’t followed the previous discussion here.

It seems that the top ceiling serves as the building envelope’s final layer with mineral wool insulation (otherwise it wouldn’t make sense). Consequently, the vapor retarder would be located below the ceiling, not at the roof. What is at the roof would then be more like a breathable roofing membrane.

However, this membrane appears to be sealed airtight at the verge and ridge, meaning there is no airflow possible under the breathable membrane.

At the coldest points, often at junctions or rafters, the breathable membrane would likely become wet.

How is the attic space ventilated permanently?
bauenmk202016 Jan 2021 19:23
parcus schrieb:

First of all, I have not followed this thread closely.
It appears that the top ceiling is the airtight envelope of the building, insulated with mineral wool. (Otherwise, it wouldn't make sense.)
Therefore, the vapor retarder should be located below the ceiling, not under the roof covering. That would mean the underlay membrane serves more as a roofing underlayment.
However, this membrane seems to be sealed airtight at the eaves and ridge, which means there is no air circulation possible beneath the underlay membrane.
At the coldest points, often the junctions and rafters, the underlay would likely become wet.
How is the attic space continuously ventilated?

How is air circulation usually implemented in a cold roof assembly? Because ours is constructed exactly as described.
P
parcus
16 Jan 2021 23:14
Water vapor is slowed down only by the vapor retarder so that the insulation continues to function; it then diffuses into the roof space and comes into contact with components such as rafters or the underlay membrane, where it condenses. This is not desirable, so ventilation is often provided through an open ridge. If the roof pitch is very shallow, additional ventilation may be opened at the eaves. In some cases, there is even a bathroom on the floor below, which leads to increased condensation above it.
A
Alessandro
21 Jan 2021 08:46
Unfortunately, I often see that the hatch of the retractable stairs is forgotten when drying the screed! Even if the cold roof is properly installed, hundreds of liters of water accumulate there! Where else should it go, if not upwards?