ᐅ Pay attention to the concrete slab foundation when building on a special or challenging site.
Created on: 3 Nov 2014 05:42
X
XinetteHello everyone,
We are planning to buy a plot in a new residential development. Construction has not started yet. The building start date is 2015.
The soil was replaced up to 4 meters (13 feet) deep due to contamination. Then, sand was added layer by layer, and each layer was compacted with heavy machinery. Local residents confirmed this to us. Finally, topsoil was applied and compacted as well. You can actually walk on it without sinking.
What do you think? Does it make sense to build on this, or will the ground still settle enough to likely cause settlement cracks? Should we expect additional costs for the foundation slab?
Best regards, Xinette
We are planning to buy a plot in a new residential development. Construction has not started yet. The building start date is 2015.
The soil was replaced up to 4 meters (13 feet) deep due to contamination. Then, sand was added layer by layer, and each layer was compacted with heavy machinery. Local residents confirmed this to us. Finally, topsoil was applied and compacted as well. You can actually walk on it without sinking.
What do you think? Does it make sense to build on this, or will the ground still settle enough to likely cause settlement cracks? Should we expect additional costs for the foundation slab?
Best regards, Xinette
Our building plot was prepared in a similar way.
It was a former factory site, with up to 6 meters (20 feet) of soil replacement (less in our case) and layered backfilling, including compaction with heavy machinery.
The soil report then provides certainty about any additional measures that need to be taken.
If I remember correctly, the concrete slab had to be reinforced with extra steel mesh and an additional layer of crushed stone had to be added.
If everything had been fully calculated for us, all of this would have cost around 4,000 euros.
However, I have also heard from other builders in the development area that they had to pay more because a greater amount of soil needed to be replaced.
It was a former factory site, with up to 6 meters (20 feet) of soil replacement (less in our case) and layered backfilling, including compaction with heavy machinery.
The soil report then provides certainty about any additional measures that need to be taken.
If I remember correctly, the concrete slab had to be reinforced with extra steel mesh and an additional layer of crushed stone had to be added.
If everything had been fully calculated for us, all of this would have cost around 4,000 euros.
However, I have also heard from other builders in the development area that they had to pay more because a greater amount of soil needed to be replaced.
B
Bauherren20143 Nov 2014 11:20The best advice is to have a soil investigation carried out (preferably before purchasing). Only then will you know if and to what extent additional costs for groundworks (e.g., soil replacement) or the foundation slab can be expected. This also depends on whether you plan to build with or without a basement. It might also be advisable to carry out a contaminated land survey.
At least the contaminated soil has been removed. Soil samples were taken continuously. We will check to see if there are any other samples available. However, I also believe that despite stabilization, there is still a possibility of further settlement.
Best regards, Xinette
Best regards, Xinette
Similar topics