ᐅ Excavation Work / Soil Investigation / Plate Load Test

Created on: 12 Oct 2019 17:08
T
Tommy77
T
Tommy77
12 Oct 2019 17:08
Hello

The groundwork contractor has temporarily completed the earthworks, which included removing the topsoil and installing a capillary-breaking layer of at least 15 cm (6 inches) of recycled gravel with a 0/45 grain size. A manhole chamber has been installed; drains, pipes, and so on will be added later. Since I’m not an expert, I have a quick question: how can I be sure that the gravel layer was installed correctly? Specifically, that it is 15 cm (6 inches) thick and properly compacted? Once compacted, you can’t really see or measure this anymore. Would a dynamic plate load test provide clarity? That test is still scheduled. Next, the shell builder will start, and I don’t know if they will check this once the slab is poured. I am building a single-family home without a basement. The soil is classified as soil class 3. The reason I ask is that I had to chase the groundwork contractor for days just to get them to start and finish… This is the only part I had to oversee; from the shell stage onward, the builder takes over. What if the groundwork contractor didn’t do a good job? Could this cause problems later, like settlement cracks? Moisture issues, too, are possible. Or is the slab itself the key factor? Thanks for your opinions and advice.

The geotechnical report mostly gives recommendations. How does that work in practice? Does anyone check this?

Construction site with earthworks, barrier tape, material stacks, and a round cover in the foreground
tomtom7912 Oct 2019 18:43
Dig a hole 20x20cm (8x8 inches), but you will soon realize that you have to wait for all the tradespeople. No one will rush to help you even if they delay you, as this is due to the high workload.
G
guckuck2
12 Oct 2019 18:54
The structural builder will measure the height. You can explicitly ask them again to double-check.
Digging a hole is a nice gesture, but it's probably better suited for a pickaxe.