ᐅ Conduct/Consequences Regarding the Construction Company

Created on: 17 Jul 2022 13:40
K
Kathi92
We have the following problem and are really at a loss now:

We started building our house in June 2021 and hired a construction company as the general contractor to deliver the turnkey project up to the finishing stage. Everything went smoothly at first, but construction then stalled due to delivery difficulties with steel/reinforcement for the intermediate ceiling. Over the winter, very little progress was made (roof, windows, and completion of brickwork). By March, the shell was finished and the roof was on.

The big problem is that the construction company continues to work at a snail's pace, which we can no longer tolerate. It has taken them a full 4 months just to complete all installations (electrical, plumbing). By the end of June, these were finally finished. To explain: they brought in an electrician from the local area who, after his regular 40-hour job, worked only about 1-2 hours in the evenings at our site. Often, he didn’t feel like working after his day job because he also wants to go home at some point. So, it dragged on forever. We didn’t even know this but found out from neighbors. This is not what we understood as subcontracting, as originally discussed. And this has been the pattern throughout. We constantly call and visit; 1. we hardly see anyone working, and 2. we are repeatedly promised, “Next week we’ll speed up,” “Our house is the top priority,” or “On day X, the interior plaster or screed will be done.” But it never happens.

We have been building for 13 months now and still haven’t even reached the stage of rough floor completion.

Originally, according to the schedule from June 2021, completion was planned for May 2022, assuming no setbacks like lockdowns. We were aware of that but made it clear at contract signing that we needed to move in by this summer at the latest (August 2022). They assured us this would work. Then they shifted to summer or June/July (due to material delivery issues).

In May, we approached them because it was already clear to us that finishing in June/July was impossible at their pace. We explained our situation: we absolutely must move in by the end of August. They said they would finish by the end of August, that they were now working continuously. We were promised drying equipment for the screed to catch up, all electricity costs covered as a goodwill gesture, and that screed and interior plaster would be done by the end of May. Then, we went on a two-week vacation in early June and came back shocked. We went to the house and nothing had happened. Zero progress. Just last week, we finally got the interior plaster. No sign of underfloor heating or screed. And the house is supposed to be handed over turnkey in about 6 weeks?

I can no longer listen to their stories and empty promises. Especially since we have an 18-month-old toddler and I am currently 5 months pregnant. So just staying in a hotel or with friends/family isn’t easy in this situation (and who pays for that?). The kitchen planner also refuses to take measurements without the screed, so we will be without a kitchen for weeks. A great situation with a child and baby. Our relationship is also suffering massively. This is the biggest source of conflict. It’s all a nightmare.

I already wanted to go to a lawyer, but what good would that do now if they can’t finish? The harshest letter won’t change anything. I can’t even count how many times we call and visit. It’s always the same empty talk. We didn’t agree on any contractual penalties due to Covid lockdowns since they couldn’t influence the construction then.

I am considering proposing that they complete the rough floor stage (screed) and then we finish the house ourselves with professional tradespeople. I think we would be much faster than them. Does anyone know what else we can do?

Thanks for reading!
A
Axolotl-neu
17 Jul 2022 20:39
Kathi92 schrieb:

Why would I voluntarily sign the contract with that clause if I then have no place to stay for 4 months?
Why did you do it?
Kathi92 schrieb:

At signing, it was said that it MUST be finished by summer at the latest. That was agreed upon. Along with the signed building plan.
No, in the contract you have December 31, 2022.

Now I’ll ask from the general contractor’s perspective: Why should I finish earlier than the date you explicitly signed in the contract? If it was so important to you, dear client, why didn’t you say so and we could have included it in the contract?

Feel free to seek legal advice, but the contract = written agreement is clear.
N
Neubau2022
17 Jul 2022 20:43
How is August 2022 supposed to be the completion date when the screed hasn’t even been installed yet? The drying process takes about 4-6 weeks. The general rule is that after the screed is poured, it takes approximately 3 months before you can proceed. So you should realistically expect completion around December and you can safely disregard August.
A
allstar83
17 Jul 2022 21:24
Neubau2022 schrieb:

How is it supposed to be finished by August 2022 if the screed isn’t even installed yet? The drying process takes about 4–6 weeks. The general rule is that after the screed is poured, it usually takes around 3 months before proceeding. So you should expect it to be done around December, and you can safely forget about August.
There are screeds that become loadable after just a few days. However, they are more expensive.
N
Neubau2022
17 Jul 2022 21:37
allstar83 schrieb:

There are screeds that can be walked on after just a few days. But they are expensive.

I don’t expect that this screed is included in the contract 😎 And screed alone is not everything. As I said, nothing will happen before December. Be prepared for that.
A
allstar83
17 Jul 2022 22:13
Neubau2022 schrieb:

I don’t expect that this screed is included in the contract 😎 Screeding alone doesn’t cover everything. As I said, nothing will happen before December. Be prepared for that.

Electricity for the fan heaters cost us several thousand euros... Just wanted to suggest that this option could also be considered. Compare that to the rent for a few months, and it balances out again.
bauenmk202017 Jul 2022 22:26
Kathi92 schrieb:

I would suggest completing the house up to the stage of ready-for-flooring (i.e., screed) and then finishing it ourselves with professionals. I think we would be much faster that way. Does anyone know what exactly we can do?

Has anyone in this forum addressed this question so far? Unfortunately, some valuable forum members who could have helped clarify this are no longer active. Early acceptance of the house is not necessarily advisable without expert advice.

What kind of contact do you have with your site manager? They are usually the one coordinating the resources. Maybe you could find out in a conversation where the current delays are—staff, materials, etc.

Otherwise, I would start looking for temporary accommodation. Unfortunately, people don’t get much sympathy when building a house and it takes longer than expected—that’s just how it is. Maybe there is an option to store furniture and such in one room of the new house. And if the flooring in that room is installed later, that’s no problem—the screed will have more time to release moisture properly.