ᐅ Single-Family Home – New Construction Project from Day One – And the Planning Begins
Created on: 7 Feb 2020 22:54
D
DaSch17
Hello dear community,
For the past few weeks, I have been following this forum and have already gathered some valuable tips for our own planning.
I would like to use this thread to keep you updated from the very first day of planning until moving in. I hope to receive some valuable advice from the community and that this thread can also serve as a guide for other first-time homebuilders.
Now, a bit about our building project:
As mentioned, we are still quite early in the process...
It all started, as it probably does for most, with requesting a catalog from a prefabricated house company. In our case, it was FingerHaus around mid-December.
This was followed by a phone call with a sales representative from the mentioned company and arranging a first consultation. This appointment is scheduled for Sunday, 09.02.2020.
Since then, we have been intensively working on budget planning, possible floor plans and building plots, as well as ideal typical living space layouts.
So far, we have not purchased a plot yet. However, we are in contact with a municipality that is currently planning an expansion of a new residential area. Fortunately, this allowed us to help decide the size, location, and shape of our future plot. Our desired plot is reserved for us.
Key details of our planned single-family home:
– Location: Southwestphalia, Siegen-Wittgenstein district
– Living area: 179 sqm (1,925 sq ft)
– Concrete slab foundation
– Gable roof
– 1.5 stories with gable roof
– Single garage with extended length for tools/storage room
Our budget:
– Plot including property transfer tax: 70,000 EUR
– Construction costs: 470,000 EUR
– Additional construction costs including earthworks: 70,000 EUR
Our schedule:
– By May 2021: Selection of the construction company
– By July 2021: Contract signing, building permit / planning permission application
– By July 2023: Completion of construction work
– By October 2023: Completion of owner-performed work (painting and flooring) and move-in
We understand that the start of construction depends on the delivery time of the prefab house company, which can vary between 6 and 24 months.
We have now selected 8 different companies with whom we want to conduct initial meetings:
– FingerHaus
– Hanse Haus
– SchwörerHaus
– Bien-Zenker
– Schäfer Haus (contact via family)
– Büdenbender Haus
– WeberHaus
– a local developer
After these initial talks, we want to proceed with more detailed discussions with 4 of these providers.
–––––––––––––––––––
What should we pay attention to during the initial meetings? What is particularly important? Should we disclose our budget to the sales representatives?
For the past few weeks, I have been following this forum and have already gathered some valuable tips for our own planning.
I would like to use this thread to keep you updated from the very first day of planning until moving in. I hope to receive some valuable advice from the community and that this thread can also serve as a guide for other first-time homebuilders.
Now, a bit about our building project:
As mentioned, we are still quite early in the process...
It all started, as it probably does for most, with requesting a catalog from a prefabricated house company. In our case, it was FingerHaus around mid-December.
This was followed by a phone call with a sales representative from the mentioned company and arranging a first consultation. This appointment is scheduled for Sunday, 09.02.2020.
Since then, we have been intensively working on budget planning, possible floor plans and building plots, as well as ideal typical living space layouts.
So far, we have not purchased a plot yet. However, we are in contact with a municipality that is currently planning an expansion of a new residential area. Fortunately, this allowed us to help decide the size, location, and shape of our future plot. Our desired plot is reserved for us.
Key details of our planned single-family home:
– Location: Southwestphalia, Siegen-Wittgenstein district
– Living area: 179 sqm (1,925 sq ft)
– Concrete slab foundation
– Gable roof
– 1.5 stories with gable roof
– Single garage with extended length for tools/storage room
Our budget:
– Plot including property transfer tax: 70,000 EUR
– Construction costs: 470,000 EUR
– Additional construction costs including earthworks: 70,000 EUR
Our schedule:
– By May 2021: Selection of the construction company
– By July 2021: Contract signing, building permit / planning permission application
– By July 2023: Completion of construction work
– By October 2023: Completion of owner-performed work (painting and flooring) and move-in
We understand that the start of construction depends on the delivery time of the prefab house company, which can vary between 6 and 24 months.
We have now selected 8 different companies with whom we want to conduct initial meetings:
– FingerHaus
– Hanse Haus
– SchwörerHaus
– Bien-Zenker
– Schäfer Haus (contact via family)
– Büdenbender Haus
– WeberHaus
– a local developer
After these initial talks, we want to proceed with more detailed discussions with 4 of these providers.
–––––––––––––––––––
What should we pay attention to during the initial meetings? What is particularly important? Should we disclose our budget to the sales representatives?
A typical prefabricated house supplier could basically be described as a timber frame general contractor, and it is definitely possible to have the house built by them following an architect’s design, just like with other general contractors. Regardless of the construction method, working with a general contractor does not automatically mean becoming a "yes-man" or "rubber-stamper."
https://www.instagram.com/11antgmxde/
https://www.linkedin.com/company/bauen-jetzt/
https://www.instagram.com/11antgmxde/
https://www.linkedin.com/company/bauen-jetzt/
That was unclear... we only had one bathroom with a bathtub on the upper floor, and one on the ground floor without. Obviously, a bathroom for children is a luxury. What would probably annoy me more is if the teenager had to go through my bedroom to take a bath. But maybe I’m only bothered by that because I’ve always really enjoyed bathing.
And now I’ll just keep my hands to myself for a while.
And now I’ll just keep my hands to myself for a while.
DaSch17 schrieb:
Basically, we still have some “open spots” available. We will follow your advice and reach out to a local architect. Additionally, we want to take a closer look at Nordhaus. Their website gave us a positive impression. Many thanks for the recommendation. Have a look at the recent report on construction defects that aired on WDR (“Könnes kämpft”). The head of Nordhaus is also featured in it.
K1300S schrieb:
Here, the CEO of Nordhaus also has a chance to speak. Dream home goodbye, going bankrupt due to poor workmanship: Nordhaus from 34:49 – I especially appreciated the comment about employed salespeople, which is rare in the industry. Also, that during a boom it’s better to take on only as much business as you can manage.
https://www.instagram.com/11antgmxde/
https://www.linkedin.com/company/bauen-jetzt/
DaSch17 schrieb:
Has anyone had experience with Duotherm walls? The search is your friend
KingJulien schrieb:
Search is your friendWell, the search function here is rather mediocre, and that only during a full moon. Combining this with an 11ant-like memory and a few additional tricks, you get results ranging from satisfactory to barely adequate. I was aware of the thread https://www.hausbau-forum.de/threads/Wasser-dringt-ins-Haus-Kern-Haus-duotherm.18308/#post-168435
for this question, but I didn’t link it here for a very simple reason: in my opinion, experiences should cover a somewhat broader spectrum. After the original poster @Jim Jones, mainly @sadrie contributed to that thread as someone affected, followed by @Sebastian02 – all users I hadn’t encountered here before, making their statements harder for me to assess; there were also responses from the involved company at the start. What I didn’t come across were comments about similar problems in other forums – and, as mentioned, other statements by those users that would help me evaluate them. So I lack enough evaluation here, which is why I refrained from linking it this time. Additionally, the Kern headquarters are geographically close to me, and I haven’t heard anything negative about them ‘from the horse’s mouth.’ This also leads me to regard the mentioned thread as more likely isolated cases.