ᐅ Payment Schedule – What Is Realistic?

Created on: 8 Nov 2010 11:40
G
Goldbeere
Hello to all readers! 🙂

After mentioning the payment schedule topic in a post related to a specific company, I would like to open a new discussion on this subject today. I want to focus on the basics first (independent of any company), and I suspect many others feel the same way. 😉

After my partner and I were presented with an "impossible" payment schedule, where an overpayment would occur after structural work, roof & windows, we tried to research what would be appropriate at this point. Overpayments are supposed to be absolutely avoided! But it’s not that easy... opinions vary widely: Some say 52%, others about 60%, and others around 70%...

Looking now at the installment payment plan according to the broker and developer regulations (which you are supposed to review for comparison, even if you are not building with a developer), I also arrive at 70.60% (30 + 28 + 5.6 + 7). So is that too much? Or are 52% too little? Someone must have come up with the broker and developer regulation payment schedule... and had a reason for it?!?

Since we have been in contact with several companies and have various payment schedules from them, I can only say that all of them (large or small construction companies alike!) are at or above about 70% at the mentioned stage.

I guess the solution lies somewhere in between?!? 🙄

Thanks for all tips and advice!!!

Goldbeere 🙂
G
Golfer911
9 Nov 2010 10:59
Hello, the best way to prevent overpayments is to contract services individually with invoice verification by an architect. That's how we did it; we worked with an architectural firm in Cologne that had an affiliated network of craftsmen nationwide. The advantage of this service provider is a fixed price as a maximum limit, no overpayments, since payment is made only after service completion and acceptance.
Best regards, Bert
N
Neu_Kieler
12 Dec 2010 08:48
Even though we are not quite at that stage yet, at the moment the banks are our main point of contact to get a clear overview of financing, we have nevertheless received a breakdown of our potential cost plan. Looking at others, I think this one is quite good.

7% after completion of the building permit / planning permission
13% after completion of building drainage, base slab / foundation
13% after completion of external and internal walls on the ground floor without cladding
13% after erecting the roof frame
13% after completion of the cladding without window sills
8% after completion of roofing and plumbing work
5% after installation of windows and external doors (without locking and fine adjustment)
5% after completion of rough electrical installation
3% after completion of drywall
3% after completion of plastering work
4% after completion of heating rough installation
3% after laying the screed
4% after laying the tiles (without baseboards)
2% after completion of heating and sanitary installation
2% after completion of electrical installation
2% after installation of internal doors

If I am mistaken, please let me know.
B
Bauexperte
12 Dec 2010 10:48
Hello,
Neu_Kieler schrieb:
...received a breakdown of our possible cost plan. Compared to others I’ve seen, I think this one is quite good.

The many payment stages give a good impression at first glance. The catch is, once the finished shell of the building is completed, you will have used up 72% of your capital. What will you do if the worst-case scenario happens? With the remaining amount, you will never be able to complete your house…

A maximum of 60% should be the upper limit for this stage of construction.

Kind regards
A
ahe
15 Dec 2010 13:41
Hello,

from personal experience: as a builder, I am currently in a very difficult situation – having paid too much for the shell construction and the build is no longer progressing...

But it is not universal – for example, if a garage is part of the construction, it must be listed separately.

Regards
Alexander
R
Regensburger
2 Jan 2011 12:48
Hello,

I am currently trying to educate myself on the subject.

If I understand everything correctly:

Is 25% payment after the start of earthworks definitely too much?

This concerns the purchase of an apartment in a six-unit building.

Regards,
Regensburger