ᐅ Duration of electrical installation (for approximately 300 switches/outlets)

Created on: 2 Jan 2019 21:14
W
wilsumer
W
wilsumer
2 Jan 2019 21:14
Hi everyone. A quick question for the electricians among you.

The plasterer is basically ready to start, but the electrician is not finished yet. I’m interested in how much time an electrician (master electrician) would typically need for the following work and conditions. Of course, I know this can’t be generalized, but a rough estimate would be sufficient since I have no idea and can’t assess this at all.

Single-family house with about 210 m² (2260 sq ft) of floor space, all on one level (former barn).
- Approximately 300 sockets and switches including satellite and network connections
- Installing the power supply from an existing electrical panel and mounting the new electrical panel including circuit breakers, etc.

All flush-mounted boxes have been plastered in and all channels have been cut. So the only work left is pulling all the cables.

How many hours could be expected for this?
B
Bookstar
2 Jan 2019 22:21
Approximately 2 days.