Hello everyone,
Construction has finally started at our site.
I would like to share my experiences, concerns, and questions about the house building process here to get feedback from experienced people.
So, it’s kind of a small building diary.
The earthworks have been completed with the delivery of 340 tons of sand for backfilling, and the trenches for the strip foundation have also been prepared.
The steel mesh for reinforcement is ready on site.
Now the date for the slab foundation is set.
Pipes for wastewater and the multi-utility connection need to be installed, the foundation grounding conductor has to be laid, a drainage membrane has to be placed, reinforcement tied, and formwork set up.
Is all of this achievable in one day, including the concrete delivery?
Before I provide more details, I’d like to hear your opinions.
Best regards
Construction has finally started at our site.
I would like to share my experiences, concerns, and questions about the house building process here to get feedback from experienced people.
So, it’s kind of a small building diary.
The earthworks have been completed with the delivery of 340 tons of sand for backfilling, and the trenches for the strip foundation have also been prepared.
The steel mesh for reinforcement is ready on site.
Now the date for the slab foundation is set.
Pipes for wastewater and the multi-utility connection need to be installed, the foundation grounding conductor has to be laid, a drainage membrane has to be placed, reinforcement tied, and formwork set up.
Is all of this achievable in one day, including the concrete delivery?
Before I provide more details, I’d like to hear your opinions.
Best regards
Okay, thanks for the information. I didn’t know that.
Then your question definitely makes sense.
As mentioned, it’s not the same company.
Then your question definitely makes sense.
As mentioned, it’s not the same company.
icandoit schrieb:
This cannot be answered in a general way.
The concrete must have a minimum temperature of +5°C (41°F) at the time of placement when the ambient air temperature at the construction site is above +3°C (37°F). If the ambient air temperature at the site is below +3°C (37°F), the concrete must have a minimum temperature of +10°C (50°F) when being placed.
And there are many other conditions.
I will send you a link via PM. Did you send me a message?
From Tuesday to Wednesday, temperatures are expected to be -13°C (9°F) at night and -6°C (21°F) during the day. The concrete is scheduled for Wednesday.
That will be canceled, right?
icandoit schrieb:
I'll help out with a link.
https://www.hausbau-forum.de/threads/das-fleischerhaus-oder-wie-es-nicht-laufen-sollte.37599/page-34#post-464790 I read through the first three pages.
Wow, what happened there is really intense.
It's pure nightmare material. I probably would have jumped off a bridge by now...
dynaudio79 schrieb:
Did you send me a message?
Yes, I did. Just now again. However, I have no idea how it works. Isn’t that the "start conversation" function?
icandoit schrieb:
Isn't that "start conversation"?Yes, you can start it already. But if the recipient hasn’t earned the permission yet, you’re sending into a void, and it won’t even appear in your outbox :-(https://www.instagram.com/11antgmxde/