ᐅ Screed Drying – Incorrect Drying Program Set

Created on: 29 Apr 2020 18:43
T
Tx-25
We realized after 12 days that our installer had set the wrong drying program. It has been running constantly at 30 degrees Celsius (86°F) for 12 days. This is an electrically powered external device, not the heat pump.
The installer is coming tomorrow. What do you recommend? I will have the screed moisture measured today. However, my main concern is the expansion. If I increase the temperature from 30 to 40 degrees Celsius (86 to 104°F) tomorrow, then from Friday to Saturday to 50 degrees Celsius (122°F), and keep it there for two days until Monday, will that be sufficient?
We have already scheduled all subsequent work steps with all contractors after the drying program. It would be a disaster if we had to extend the program.
G
guckuck2
4 Jul 2020 12:03
In bad weather? I don't think so.
Vicky Pedia4 Jul 2020 12:31
bauenmk2020 schrieb:

@Vicky Pedia
The heat pump hasn’t been installed yet. Ventilate to get the warm, humid air out. Would a dehumidifier have been more effective?
Certainly, but that is usually done only after 4 weeks and it also consumes electricity.