ᐅ Which trades come after the shell construction?

Created on: 12 Jun 2017 12:17
S
skyboy89
Hello everyone,

On Saturday, we raised our roof frame.
Next, the gable will be built up with masonry, followed by roofing and so on.

Now my question:

What order would you recommend for the following trades? I am particularly interested in electrical work, plumbing, heating, screed, plastering, and so on.

Thank you for your help.
N
nightdancer
12 Jun 2017 21:49
Of course, heating, plumbing, and electricians can start work before the window installation. I also applied the base coat with gypsum plaster indoors before installing the windows and screed. This saves time. The electrical chases were filled afterward. After the windows are installed, the screed comes next, followed by filling, sanding, painting, floor coverings, doors, and the final installation of electrical and plumbing fixtures.