ᐅ Which trades come after the shell construction?

Created on: 12 Jun 2017 12:17
S
skyboy89
S
skyboy89
12 Jun 2017 12:17
Hello everyone,

On Saturday, we raised our roof frame.
Next, the gable will be built up with masonry, followed by roofing and so on.

Now my question:

What order would you recommend for the following trades? I am particularly interested in electrical work, plumbing, heating, screed, plastering, and so on.

Thank you for your help.
S
Steffen80
12 Jun 2017 12:24
Electrical
Plastering
Heating
Screed
Electrical / Plumbing
Painting
Floor coverings
Electrical / Plumbing
F
Flose89
12 Jun 2017 12:26
I was about to say the same. Just enter "construction schedule" in Google. There are a few good ones available.
M
matte
12 Jun 2017 12:28
Steffen80 schrieb:
Electrical
Plastering
Heating
Screed
Electrical / Plumbing
Painter
Flooring
Electrical / Plumbing


Shouldn't the rough-in work for heating and plumbing be done before plastering as well?
Mycraft12 Jun 2017 12:33
Yeah... I would definitely install those right after the walls, even before the electrician.
S
Steffen80
12 Jun 2017 12:39
matte1987 schrieb:
Shouldn't the rough-in for heating/plumbing be done before plastering?

It depends. For us, it was ONLY the outdoor water tap. The rest is installed inside wall cavities.