ᐅ Which level of finishing is appropriate for an attic reserved for future expansion?

Created on: 30 Jul 2019 22:41
A
allstar83
A
allstar83
30 Jul 2019 22:41
Hello everyone,

We are currently in the initial discussions with suppliers for a new single-family home with a gable roof. The attic is planned as a future living space while the children are still small and will be used until then as storage, a playroom, and a basement substitute.

Unfortunately, everyone says something different regarding the "stage of completion" that should be commissioned initially so that a possible later conversion does not involve too much work.
The house is planned with underfloor heating on the ground floor and district heating.

What would you recommend including in a house built by a general contractor to be able to "use" the attic in its unfinished state as described above?
  • Insulation of the concrete ceiling or roof insulation?
  • Have the screed installed right away?
  • Would it possibly make sense to completely skip underfloor heating in the attic (because the room layout is still unknown) and just have screed installed?
  • Install windows upfront or keep everything closed?
  • Have pipes and wiring pre-installed running up to the attic?
  • Plaster the attic walls?
  • etc.

It would be great if someone could share tips and experience about which combinations make sense here.

Thanks and best regards
A
allstar83
31 Jul 2019 23:52
Experience or practical insights would be great.
Dr Hix1 Aug 2019 00:33
Insulating the ceiling instead of the roof is possible, but it costs money for suitable insulation material (walkable) and flooring. If you insulate the roof directly, you should also provide heating and consequently include underfloor heating and screed at the same time.

Screed would be necessary anyway for underfloor heating. Installing screed without underfloor heating means having to change the heating concept later or removing the screed again.

Windows in the masonry should at least already be planned. Blocking up these openings later instead of installing windows right away does not offer any significant cost savings. The only option might be to initially omit double casement windows and just provide a few lintels at the appropriate locations.

Pipes should definitely be routed upwards at the same time; they cost hardly anything, and you will need electricity up there anyway.

Plastering the walls depends on the interior finish. If screed and flooring are already installed, you probably won’t want a plasterer coming in later. Still, here I see at most a few hundred euros worth of potential savings on a few square meters of gable masonry.

In short: If it is already certain that these rooms will be needed later, it’s definitely best to include them now—not least because they will then already be approved. The 2–3k you might “save” now do not justify the hassle.
H
hanse987
1 Aug 2019 00:58
I would definitely plan out where each room might be located. It’s not just about electrical installations but also about water supply and drainage if you are planning a bathroom or toilet. Additionally, things like satellite TV or network connections shouldn’t be overlooked.

If it is already certain that you will be using these rooms in the future, it makes sense to have everything installed at once.
A
allstar83
3 Aug 2019 17:02
Thank you for the input.

We will probably just have the screed installed to have a proper floor and insulate the ceiling below. The roof, however, will not be insulated at this stage. Connections will be raised. If we decide to fully finish the space in the future, a few standard radiators will have to suffice.

Windows in the exterior walls are planned. However, the attic will definitely not have a bathroom or WC installed. It will basically be used only for storage or hobby rooms.
E
Egberto
3 Aug 2019 17:14
You might also consider a heating system integrated into the wall surface, similar to underfloor heating but for the walls, which doesn’t require additional floor construction.