from when is it possible to start the painting work in the finished living area (FLA)? Do certain drying processes need to be waited for? For example, only after the screed heating phase, or is that not relevant?
Thanks!
from when is it possible to start the painting work in the finished living area (FLA)? Do certain drying processes need to be waited for? For example, only after the screed heating phase, or is that not relevant?
Thanks!
Painting is done once the interior plaster and screed are dry. There are three steps: filling, sanding, and painting or rolling. Alternatively, wallpapering can be done, which reduces the amount of filling required.
The flooring is installed last. The door frames should already be mounted before painting, as they need to be worked around.
The flooring is installed last. The door frames should already be mounted before painting, as they need to be worked around.
F
fach1werk1 Apr 2020 08:19I find it advantageous to work from top to bottom, starting with the ceilings. Before applying filler, if filling is necessary, you should first run a trowel lightly over the surface to lift any high spots. Check surfaces in raking light beforehand.
I think finishing the surfaces is satisfying work because you can clearly see the results.
Enjoy the process,
Gabriele