ᐅ Shell construction completed, next steps for interior finishing
Created on: 8 Sep 2017 06:35
H
HRG83
Hello everyone,
I have a question about the sequence of work. Our shell construction is completed. Is the following process correct, as we are coordinating everything through self-management?
* Windows are ordered
* Utility connections will be installed in week 38
* Insulating the roof
Once windows and doors are installed, then:
* Rough-in electrical/plumbing/heating
* Installing interior window sills
* Interior and exterior plastering
* Screed
* Electrical/heating installation
* Fireplace
* Tiling
* Flooring
When is the ceiling on the upper floor covered with drywall (gypsum board), and when is the attic ladder installed?
Thanks
I have a question about the sequence of work. Our shell construction is completed. Is the following process correct, as we are coordinating everything through self-management?
* Windows are ordered
* Utility connections will be installed in week 38
* Insulating the roof
Once windows and doors are installed, then:
* Rough-in electrical/plumbing/heating
* Installing interior window sills
* Interior and exterior plastering
* Screed
* Electrical/heating installation
* Fireplace
* Tiling
* Flooring
When is the ceiling on the upper floor covered with drywall (gypsum board), and when is the attic ladder installed?
Thanks
B
Bau-Schmidt19 Sep 2017 08:42HRG83 schrieb:
The utility connections will be installed next week. Although the shell is not yet closed, I have secured the technical room in the basement with a construction door for the main service panel. The room where the connections will be installed only needs to be lockable.