What does the soil report say? Temporarily accumulating seepage water? Who actually makes the recommendations... the architect? The general contractor?
A bit of background information could help to provide a more specific response.
For example, in our case: the soil report indicates clayey soil with temporarily accumulating seepage water... so there is no question -> waterproof concrete, formed and poured.
Otherwise, if there are no reasons for one option or the other, I would choose the cheaper one [emoji6]
A bit of background information could help to provide a more specific response.
For example, in our case: the soil report indicates clayey soil with temporarily accumulating seepage water... so there is no question -> waterproof concrete, formed and poured.
Otherwise, if there are no reasons for one option or the other, I would choose the cheaper one [emoji6]