ᐅ Positioning of the Electrical Service Connection Column – New Construction

Created on: 12 May 2024 22:52
J
Jolo200000
J
Jolo200000
12 May 2024 22:52
Hello,

We are unsure about the placement of the utility connection pillar. The electrical service connection will be installed soon.
Maybe someone has a tip (there aren’t many options for such a small plot)…

Thank you very much!
Detailed construction and site plan with planned terrace, driveway, and landscaping.
K
kbt09
13 May 2024 07:21
Where is the utility room located? The crystal ball is currently out of service. Also, is a garage or carport planned to be placed on the right side of the house?
J
Jolo200000
13 May 2024 16:51
Sorry (true - the utility room is of course not visible). The utility room is located at the very front right of the house, where the utilities come together – water, sewage... – (multi-utility entry).
The driveway is on the far right and is planned with a carport.
S
sysrun80
13 May 2024 23:11
Quick question: Is the meter cabinet only temporary, or does it remain after completion? We only had one during the shell construction phase, but it was removed afterward and the connection was routed directly into the multi-service duct.
J
Jolo200000
13 May 2024 23:14
That's right – if it were possible for me, temporary would of course be better. The utility connection pillar should remain in place (but maybe this option is also feasible, then the box wouldn’t be an issue). I will ask again.
Y
ypg
13 May 2024 23:15
I would also like to know what purpose this column is supposed to serve. The electrical panel will be installed in the utility room; all cables come underground and through a frost-protected installation from the service connection at the street, entering through the exterior wall. Or is it different in your case?