ᐅ Timeframe Between Submitting the Building Application and Moving into the New Home
Created on: 14 Jun 2020 13:27
P
PinkiponkP
Pinkiponk14 Jun 2020 13:27On average, eight months pass in Germany between submitting the building permit application for your dream house and moving in.
Can anyone confirm this? I just read this "statistical value" (?) in a "home magazine" and I am curious about its accuracy. If this is true, that would be great. However, I have never heard or read this figure anywhere else.
Thank you.
Can anyone confirm this? I just read this "statistical value" (?) in a "home magazine" and I am curious about its accuracy. If this is true, that would be great. However, I have never heard or read this figure anywhere else.
Thank you.
The average time between submitting the building permit / planning permission application and receiving approval is about 3 months.
The construction company usually takes one month to start (unless they have no other projects), and building a house takes around 7 months... Viebrockhaus is faster with temporary tent structures, while others take longer.
As a general rule, I would estimate about one year if using a general contractor. With individual contracts, expect an additional six months to one year.
The construction company usually takes one month to start (unless they have no other projects), and building a house takes around 7 months... Viebrockhaus is faster with temporary tent structures, while others take longer.
As a general rule, I would estimate about one year if using a general contractor. With individual contracts, expect an additional six months to one year.
N
NatureSys14 Jun 2020 17:40Less than a year from the submission of the building permit / planning permission is already quite fast.
H
hampshire14 Jun 2020 18:00Submitted at the end of May / beginning of June 2018, approved at the end of August 2018, groundwork and foundation slab completed by March 2019, move-in August 2019. For us, that means 14-15 months from submitting the building permit / planning permission application to moving in, roughly the same duration as the preceding planning phase.