ᐅ Is it possible for a concrete slab to have sufficient load-bearing capacity after 24 hours?
Created on: 22 Aug 2018 22:14
D
denz.Good evening,
Our foundation slab is scheduled to be poured tomorrow. The blocks (calcium silicate bricks) will be delivered on Friday and the following Monday. They are planned to be stored on the foundation slab.
Is this normal? I thought the foundation slab would need a few days before heavy materials like this could be placed on it.
Regards, denz
Our foundation slab is scheduled to be poured tomorrow. The blocks (calcium silicate bricks) will be delivered on Friday and the following Monday. They are planned to be stored on the foundation slab.
Is this normal? I thought the foundation slab would need a few days before heavy materials like this could be placed on it.
Regards, denz
R
readytorumble23 Aug 2018 07:53It was the same for us; nothing happens anymore.