ᐅ Floor plan design shortly before submitting the building permit application

Created on: 2 Oct 2017 23:25
R
R.Hotzenplotz
Hello everyone!

As some users have requested before, I’m now starting a new thread with the current planning of our detached house, which is about to be finalized.

These are the preliminary drawings for the building permit / planning permission application, and I have one last chance to review them and point out any issues.

It still seems to me that there is less than 1.20m (4 feet) of space between the two wardrobes in the dressing room. Or am I seeing this wrong? Apparently, the rooms on the left and right were overlooked and not adjusted accordingly.

Two Velux ceiling spotlights are still planned to illuminate the upper floor hallway.

In the basement, on the right side in the upper room, a window similar to the one on the left basement side is an option.

We still haven’t decided on the T30 fire-rated door to the garage, even though it is shown in the plans. Most likely, for safety reasons and the limited use of the kitchen at the other end of the house, we will eventually forgo it.

User 11ant pointed out that the right window in child’s room 2 is suboptimally positioned. However, this could still be changed after submitting the building permit / planning permission application. Our architect thinks moving the window to the left would negatively affect the house’s exterior appearance. We’ll have to see about that.

Grundriss Kellergeschoss mit 3 Kellerräumen, Abstellraum, Flur, Haustechnik und Treppe.


Grundriss eines Hauses mit Keller, Flur KG, Haustechnik KG, Abstellraum KG und Treppen


Grundriss eines Hauses: Garage, Büro, Garderobe, Diele, WC, Küche, Wohn-/Essbereich.


Grundriss Dachgeschoss: Schlafzimmer, Ankleide, Bad, Dusche, zwei Kinderzimmer, Flur HWR Dachterrasse


Technischer Grundriss: Zentraler, ungenutzter DG-Bereich (193 m²) mit umlaufenden Dachschrägen.


Schnitt durch mehrstöckiges Wohnhaus mit Keller, Treppe, Dachkonstruktion und Maßlinien.


Moderne Wohnhausansicht: zweigeschossiges Gebäude mit Garage links und großen Fenstern.


Architektonischer Haus-Elevationsplan: Keller bis Dachgeschoss, Dach, Fenster, Geländeprofil.


Moderne zweigeschossige Hausansicht mit Flachdach, Balkonen, großen Fenstern und Garage.


Zweistöckiges Haus mit dunkler Fassade, grauem Dach, Balkon rechts und Garten mit Bäumen.
11ant15 May 2018 14:05
R.Hotzenplotz schrieb:
but the site manager says that by the final deadline at the beginning of October, nothing is expected to change because they regularly make up for lost time in the structural shell phase during the interior finishing phase.

I don’t believe that – unless they have an army of their own “screed Ahmeds.”
haydee schrieb:
The companies and tradespeople already knew each other and have worked together before

But will they still get along when they’re constantly getting in each other’s way on site?

There are hardly any ways to catch up beyond those two (“additional own workforce of helpers” and “having trades working simultaneously instead of one after the other”). Otherwise, the only other option I can think of is switching to “fast-drying” materials. Overtime has probably already been maxed out given the current workload.
https://www.instagram.com/11antgmxde/
https://www.linkedin.com/company/bauen-jetzt/
H
haydee
15 May 2018 14:48
Dear no, not necessarily. There were definitely some heated arguments.
In some cases, it went better where the trades overlapped.
Especially the drywall installer was familiar with the quirks of the electricians and the plumbers.
R
ruppsn
15 May 2018 14:55
Well, our neighbors started their construction exactly one year ago. They worked with a locally based general contractor, and the house was ready for occupancy by mid-October. They moved in during the first week of November, based on their own preference. The build is solid, with no shoddy work—it just went smoothly. So yes, it’s possible; no need to panic.

For us, construction will probably start soon as well, but we are building with an architect, not a general contractor. I expect the construction period to be about 9 months. There is quite a difference between having everything managed by one party or contracting individual trades separately. Celebrating Christmas this year in our own home seems unlikely, but I wouldn’t give up hope for you yet.
bau.mal15 May 2018 15:05
R.Hotzenplotz schrieb:
For the period after nine months, a compensation amount was contractually agreed in advance. Therefore, there is indeed significant pressure.

You’re probably the only one who believes that; not advising, not helping.
R
R.Hotzenplotz
15 May 2018 15:41
Bau.mal schrieb:
You’re probably the only one who believes that; not advising or helping someone.

Okay, maybe not heavy pressure. But at least I have covered any potential additional costs on my side. Therefore, I will not create artificial pressure and risk poor workmanship. It will be finished when it is finished. I remain relaxed about it.
R
R.Hotzenplotz
15 May 2018 21:30
Now everything is really coming together. The neighbor is complaining that the property boundary was not respected and that his bushes were destroyed. In fact, he sent photos showing gravel compacted on his property.

He also complained that the stone cutter machine seems to be broken, and now a cutoff grinder is being used, which creates a lot of dust. But there’s probably nothing he can do about that, or is there?