Hello dear forum members,
I’m still quite unsure whether it’s better nowadays to build with a developer or with an architect. We are currently gathering house construction offers.
A short introduction about us:
We are currently a household of four. We will purchase the plot from our own funds, including property transfer tax and notary fees (no commission applies). The plot size is about 600 m2 (approximately 6,460 sq ft). The plot is designated as a building site and is fully developed (a building permit / planning permission could be obtained in 3-4 weeks). We only need to arrange the connection to the utility shaft (which is not far away).
Our wishes for the house:
A 1.5-story house (about 120 - 130 m2 (1,290 - 1,400 sq ft)) with a pitched roof, with storage space in the attic.
Upper floor: 3 children’s rooms, bedroom, large bathroom.
Ground floor: open kitchen, dining and living area, guest bathroom, heating/utility room, possibly a storage room behind the kitchen.
Underfloor heating throughout, corner bathtub, anthracite-colored roof as well as anthracite-colored windows, shutters on the windows. We want to build a double garage ourselves step by step, only the foundation slab should be poured professionally. No fireplace, no basement. We want to build solidly and cost-effectively but with good quality—so not the cheapest of the cheap, but no extravagant features like golden faucets either.
We plan to do the exterior landscaping, painting and wallpapering work, as well as floor coverings (except tiles) and the garage (except for the foundation) ourselves later on.
We already visited an architect who couldn’t provide exact figures yet, as he first wants to develop the floor plan with us. We also met with a developer (Town & Country). In the first meeting, they already gave us figures. Now we are skeptical whether these numbers are realistic or just nicely calculated. We are also uncertain whether to build with a developer or an architect. We have heard a lot of stories about poor workmanship by developers, and that contracts often have loopholes. So far, we have not heard any negative feedback about Town & Country regionally, so we had a first consultation with this developer. The salesperson was very friendly and patiently explained many things, but of course, they also want to make a sale. We now believe that the numbers may have been presented too favorably. Therefore, we are asking experienced builders for advice on whether this looks realistic so far...
The following was calculated in the first meeting: (We emphasized that we do not want additional financing later and therefore don’t want the calculation to be too tight.)
Construction and ancillary costs:
Our house with Town & Country (Lichthaus) with the mentioned rooms and special requests (house color: light yellow (possibly another color, just an example), underfloor heating throughout, corner bathtub, anthracite-colored roof, anthracite-colored windows, shutters on the windows)
€199,170
Connection fees and costs (water, wastewater, electricity, gas, sewer connection): €10,000
Cost for foundation reinforcement, foundation height increase: €5,000
Soil excavation removal: €1,000
Construction water and power connection: €1,000
Materials for wallpapering and floor coverings: €5,000
Materials for the exterior landscaping: €5,000
Garage 6x8 m (20x26 ft) foundation slab: €8,000
Site plan, staking out, permit fees, other fees: €3,500
Interest during construction period: €2,500
Contingency for selections, kitchen: €10,000
Additional notary fees: €1,000
Total costs: €251,170
This would be the loan amount we would need to take out. Own work and the plot are already deducted.
Sounds pretty good overall, but we are skeptical whether the numbers are just presented too nicely or if something is still missing.
For example, where exactly are the surveying costs accounted for? All included in the €3,500? Is that realistic?
I’ve often read online that the cost for construction water and power connection is usually around €2,000. What exactly do they mean by connection here? I thought this referred to the consumption during construction. The plot should already be connected with the calculated €10,000, right?
Also, we wanted to plan €10,000 for the kitchen. That means there is €0 contingency for selections included. I think you usually need to budget at least another €10,000 for fittings. He always said they already have nice standards and if we don’t want golden faucets, this should be sufficient. According to my online research, however, these standards are often very basic and not always very attractive. Of course, we don’t want golden faucets or exaggerated features, but it should be a bit nice, so you’d still want to budget some contingency for selections...
Is something missing in the above initial overview, or is the estimate really too low? I appreciate your experience, feedback, and tips. Also regarding the developer Town & Country.
Best regards
I’m still quite unsure whether it’s better nowadays to build with a developer or with an architect. We are currently gathering house construction offers.
A short introduction about us:
We are currently a household of four. We will purchase the plot from our own funds, including property transfer tax and notary fees (no commission applies). The plot size is about 600 m2 (approximately 6,460 sq ft). The plot is designated as a building site and is fully developed (a building permit / planning permission could be obtained in 3-4 weeks). We only need to arrange the connection to the utility shaft (which is not far away).
Our wishes for the house:
A 1.5-story house (about 120 - 130 m2 (1,290 - 1,400 sq ft)) with a pitched roof, with storage space in the attic.
Upper floor: 3 children’s rooms, bedroom, large bathroom.
Ground floor: open kitchen, dining and living area, guest bathroom, heating/utility room, possibly a storage room behind the kitchen.
Underfloor heating throughout, corner bathtub, anthracite-colored roof as well as anthracite-colored windows, shutters on the windows. We want to build a double garage ourselves step by step, only the foundation slab should be poured professionally. No fireplace, no basement. We want to build solidly and cost-effectively but with good quality—so not the cheapest of the cheap, but no extravagant features like golden faucets either.
We plan to do the exterior landscaping, painting and wallpapering work, as well as floor coverings (except tiles) and the garage (except for the foundation) ourselves later on.
We already visited an architect who couldn’t provide exact figures yet, as he first wants to develop the floor plan with us. We also met with a developer (Town & Country). In the first meeting, they already gave us figures. Now we are skeptical whether these numbers are realistic or just nicely calculated. We are also uncertain whether to build with a developer or an architect. We have heard a lot of stories about poor workmanship by developers, and that contracts often have loopholes. So far, we have not heard any negative feedback about Town & Country regionally, so we had a first consultation with this developer. The salesperson was very friendly and patiently explained many things, but of course, they also want to make a sale. We now believe that the numbers may have been presented too favorably. Therefore, we are asking experienced builders for advice on whether this looks realistic so far...
The following was calculated in the first meeting: (We emphasized that we do not want additional financing later and therefore don’t want the calculation to be too tight.)
Construction and ancillary costs:
Our house with Town & Country (Lichthaus) with the mentioned rooms and special requests (house color: light yellow (possibly another color, just an example), underfloor heating throughout, corner bathtub, anthracite-colored roof, anthracite-colored windows, shutters on the windows)
€199,170
Connection fees and costs (water, wastewater, electricity, gas, sewer connection): €10,000
Cost for foundation reinforcement, foundation height increase: €5,000
Soil excavation removal: €1,000
Construction water and power connection: €1,000
Materials for wallpapering and floor coverings: €5,000
Materials for the exterior landscaping: €5,000
Garage 6x8 m (20x26 ft) foundation slab: €8,000
Site plan, staking out, permit fees, other fees: €3,500
Interest during construction period: €2,500
Contingency for selections, kitchen: €10,000
Additional notary fees: €1,000
Total costs: €251,170
This would be the loan amount we would need to take out. Own work and the plot are already deducted.
Sounds pretty good overall, but we are skeptical whether the numbers are just presented too nicely or if something is still missing.
For example, where exactly are the surveying costs accounted for? All included in the €3,500? Is that realistic?
I’ve often read online that the cost for construction water and power connection is usually around €2,000. What exactly do they mean by connection here? I thought this referred to the consumption during construction. The plot should already be connected with the calculated €10,000, right?
Also, we wanted to plan €10,000 for the kitchen. That means there is €0 contingency for selections included. I think you usually need to budget at least another €10,000 for fittings. He always said they already have nice standards and if we don’t want golden faucets, this should be sufficient. According to my online research, however, these standards are often very basic and not always very attractive. Of course, we don’t want golden faucets or exaggerated features, but it should be a bit nice, so you’d still want to budget some contingency for selections...
Is something missing in the above initial overview, or is the estimate really too low? I appreciate your experience, feedback, and tips. Also regarding the developer Town & Country.
Best regards
Winniefred schrieb:
I’m out of here. I don’t feel like spending my free time dealing with what others consider ridiculous about what I write, especially when they obviously haven’t read my posts carefully. I apologize if I misunderstood something. To me, it sounded like you wanted to compare a detached house with a basement, garage, and shed to a 120m² (1300 sq ft) house for 5 people without a basement, garage, or shed.
N
Newcomer1236 Aug 2019 20:02Yosan schrieb:
Is there still interest in me comparing your calculations with our numbers?Yes, very much so. Maybe you could also include how many square meters (square feet) of living space you had.Furthermore, it is really difficult to keep a too-small house without storage spaces tidy when you have children. We are currently living in a small mid-terrace house. Two of us moved in here. Back then, it was great. The children's room was used as a storage space, and the converted attic with a gallery served as an office and laundry drying area. Meanwhile, two children now live in the only children’s bedroom. The attic with the home office space is our only storage option and is now just completely cluttered. The open but small living/dining area is taken over by the children in every corner. There are always things lying around because many items simply no longer have a fixed place. That’s really frustrating! I'm looking forward to our soon much larger space in square meters (square feet).
Newcomer123 schrieb:
Yes, gladly. Maybe you could also mention how much living space in square meters you had. Okay, we are building the Flair 152re (with an extension, but I will leave that out here).
So, besides the house price and the contractually agreed changes (heat pump, barrier-free showers, etc.), the following costs occurred:
Additional foundation costs 6,500 (in the end 6,400)
Excavated soil removal 2,500
Construction water/electricity 2,000
Painting/flooring work 9,000 (of which 6,000 was own labor, the rest materials)
Outdoor landscaping 16,000 (6,000 own labor, rest materials)
Inspection shaft, lifting unit or similar 5,000
Surveying fees and other charges 3,500
Construction period interest 2,500
Mortgage registration fees 2,580