ᐅ Correct Sequence

Created on: 21 Nov 2012 13:44
S
stelim
S
stelim
21 Nov 2012 13:44
Hello everyone,

I would appreciate some expert advice on how to arrange the following renovation tasks in the correct chronological order. The following work needs to be completed:

- Replacement of the heating system including radiators
- Window replacement
- Bathroom renovation
- Construction work (removing one wall, bricking up one door)
- New interior doors including door frames
- New flooring throughout the entire house

Thank you in advance!
B
Bauexperte
21 Nov 2012 14:17
Hello,
stelim schrieb:

I need some expert advice on how to arrange the following renovation steps for a house in the correct chronological order.

- Construction work (remove one wall, brick up one door)
- Replacement of heating system including radiators
- Replacement of windows
- Bathroom renovations
- New flooring throughout the entire house
- New doors including door frames

That seemed like a simple question 😎

Kind regards
S
stelim
21 Nov 2012 15:34
Bauexperte schrieb:
Hello,

- Construction work (removing one wall, bricking up one door)
- Replacement of heating system including radiators
- Replacement of windows
- Bathroom renovation
- New flooring throughout the entire house
- New doors including door frames

That was actually a simple question 😎

Kind regards

Thank you very much in advance :-) I’m still in the planning phase, so more complicated questions will definitely come up 😉