Two masons can complete a straight floor of a single-family house in two to three days. For a bungalow, add one day due to its size.
The slopes of a gable take slightly longer but not significantly more time; this applies to a pitched roof regardless of the ceiling height. Additionally, erecting scaffolding is required.
Overall, the masonry work does not take a considerable amount of time.
This is something I have observed at several nearby construction sites.
The slopes of a gable take slightly longer but not significantly more time; this applies to a pitched roof regardless of the ceiling height. Additionally, erecting scaffolding is required.
Overall, the masonry work does not take a considerable amount of time.
This is something I have observed at several nearby construction sites.
B
Bauexperte27 Jun 2016 14:37Evolith schrieb:
Quick question: how does the construction time of a bungalow compare to that of a multi-story house? Not at all 😉
Regards, Bauexperte