ᐅ Building without detailed construction planning if...

Created on: 4 Feb 2015 08:28
T
Tagtraum85
Good morning dear forum,

as the title suggests, I have a question regarding the detailed design phase, but unfortunately, I need to provide some background first:

We worked with an architect on the planning permission stage, and the building permit / planning permission application has been submitted. We have a friend who is a contractor (civil and structural works) supporting us privately with our project. He recommended an engineering firm for phases 6-9 (execution planning and supervision), with whom he likes to cooperate because they are both technically skilled and personally reliable.

We have now met with the engineering firm. They will handle the commercial aspects and the tendering, and one of their engineers is an energy consultant and building surveyor who would take over the site management / construction supervision. So far, so good.

Now to the main reason for my question:
The future site manager has reviewed our plans and found them very good. So good, in fact, that he suggested, once he receives the structural engineer’s plans and possibly one or two additional detailed drawings (including floor and roof construction), we could forego the execution planning phase. After a brief discussion with our contractor friend, this would be possible but would mean more coordination effort for the site manager.

Naturally, we are somewhat uncertain. On the one hand, we want to build a house without major defects or problems, but on the other hand, this option is financially tempting for us.

Can we rely on the statement of the site manager, who is also a building surveyor, or how would you proceed? What can we do to avoid any pitfalls?

Thank you in advance for your answers.

If any additional information is needed, I am happy to provide it.

Best regards

P.S.: Maybe it’s important to mention: we are building a fairly “simple” house in terms of structure, with no complicated walls or ceilings as far as I can judge.
Jochen10429 Dec 2015 11:17
Ours was also 1:50.
EveundGerd29 Dec 2015 13:25
Ours was also at a scale of 1:50. Some details were still shown in much larger scale. Completed, discussed, and signed before the project started; without this, the general contractor wouldn’t have even poured the foundation slab.