ᐅ New Build KfW 55 EE: Differing Opinions Between Energy Consultant and General Contractor

Created on: 4 Feb 2022 22:19
H
HausJam
H
HausJam
4 Feb 2022 22:19
Hello everyone,

We are currently in the final stages of planning our KfW 55 EE single-family house (the application has already been approved).

During the planning phase, our main contractor provided the energy consultant with a list of building components, which the consultant then used to complete the KfW 55 EE calculation. However, the energy consultant considers the listed components insufficient and therefore recommends the following changes to meet the KfW 55 EE standard:
  • Ground slab
    • Additional insulation below the ground slab: XPS 100 mm (4 inches)
  • Exterior basement walls (north, east, south)
    • Insulation: XPS 160 mm (6 inches) instead of EPS 120 mm (5 inches)
  • Exterior basement wall (west only) + exterior walls on the ground floor and upper floor
    • Aerated concrete 008 instead of 009
  • Roof
    • Above-rafter insulation PU 140 mm (6 inches) instead of under-rafter insulation 50 mm (2 inches) glass wool
Attached are the two building component lists from the energy consultant and the main contractor, as well as excerpts from the energy consultant’s calculation.

The main contractor now believes that the additional insulation measures are unnecessary and only included because the energy consultant applied a blanket calculation for thermal bridges.

We now have the following questions:
  • Are the building components proposed by the main contractor sufficient for a KfW 55 EE house, or are they far from the standard?
  • Are the extra measures demanded by the energy consultant unnecessary?
  • How much heating cost savings can roughly be expected from the additional insulation?
  • Can anyone provide a rough estimate of the costs for the additional measures?
We are simply unsure who is correct in their opinion and whether it is worthwhile to pay the extra costs for a better-insulated house or if, as the main contractor suggests, the additional measures are unnecessary and it would be better to have the thermal bridges calculated individually...

Thanks in advance!

HausJam

Detailed construction planning with ground slab, insulation, and walls


Component and material list of a construction project: ground slab, walls, windows, roof, heating.


Component overview H't: table with area, U-value, H’T, Fx and H’T*Fx of all components.


Table with energy efficiency data of the building: efficiency house level, QP, H’T, EE class


Two-tier table: living area and basement windows with correction factor, U-value, and glazing.


Calculated U-values and material layers for basement ground slab, basement exterior wall, soil.


Technical table: U-value and thermal resistance of exterior wall (36.5 cm) and insulated roof.
11ant4 Feb 2022 23:46
HausJam schrieb:

We are currently in the final stages of planning our KfW 55 EE single-family home (the application has already been approved).

Which one exactly: the building permit / planning permission or the KfW funding application?
https://www.instagram.com/11antgmxde/
https://www.linkedin.com/company/bauen-jetzt/
H
HausJam
5 Feb 2022 00:05
11ant schrieb:

Which one exactly: the building permit / planning permission or the application for KfW funding?

Ah, sorry, I wasn’t quite clear. The funding from KfW.
T
TmMike_2
5 Feb 2022 08:12
Don’t you have a fixed price agreement with gü? He should complete that properly for free then 😉
H
HausJam
5 Feb 2022 10:25
TmMike_2 schrieb:

Don’t you have a fixed price with the general contractor? He should just do that properly for free;)
The contract with the general contractor hasn’t been signed yet. There were still a few issues to clarify regarding the scope of work, but the KfW application had to be submitted before that. Overall, it will be a fixed price, which we will finalize next Wednesday.
P
parcus
5 Feb 2022 10:33
The relatively poor exterior walls have to be compensated for somehow, as their surface area is simply too large.
Often, only the roof and the windows remain as options, hence the ideal values 🙂
For me, the question would be more about the thermal bridge verification, or rather, what kind of thermal bridge allowance was applied at all.